液化天然气接收站蒸发气回收优化技术
引用本文:曹玉春,陈其超,陈亚飞,胡巍亚.液化天然气接收站蒸发气回收优化技术[J].化工进展,2016,35(5):1561-1566.
作者姓名:曹玉春  陈其超  陈亚飞  胡巍亚
作者单位:常州大学石油工程学院, 江苏 常州 213016
基金项目:常州市科协自然基金项目(常科协〔2011〕40号)。
摘    要:以大连液化天然气(LNG)接收站为例,利用Aspen软件对LNG接收站蒸发气(BOG)处理工艺流程进行分析。提出了BOG再冷凝液化与直接压缩混合使用的运行方案,并且在再冷凝工艺流程中增加预冷装置。分析结果表明:当接收站能够稳定提供足够量LNG时,系统优先选择再冷凝工艺路线,否则自动切换至高压压缩工艺路线,并直接输送至管网。该混合使用方案能够解决因储罐及管网内BOG压力过高而放空所造成的能源浪费问题。再冷凝工艺流程中,加装预冷装置之后,压缩机较加装之前节约能耗37.4%。

关 键 词:液化天然气  蒸发气  再冷凝  直接压缩  预冷  
收稿时间:2015-10-26

The optimization of BOG recycling at LNG receiving terminal
CAO Yuchun,CHEN Qichao,CHEN Yafei,HU Weiya.The optimization of BOG recycling at LNG receiving terminal[J].Chemical Industry and Engineering Progress,2016,35(5):1561-1566.
Authors:CAO Yuchun  CHEN Qichao  CHEN Yafei  HU Weiya
Affiliation:School of Petroleum Engineering, Changzhou University, Changzhou 213016, Jiangsu, China
Abstract:With the Dalian liquefied natural gas (LNG) terminal as the example, the boil off gas (BOG) treatment process was analyzed using Aspen software. The combined operations of BOG re-condensation liquefaction and direct compression was proposed, as well as adding pre-cooling device in the re-condensing process . The analysis results show that if the receiving station can supply sufficient amount of LNG stably, the re-condensation process route will be chosen in priority, otherwise the system will be switched to the high-pressure compression process line automatically, and transported LNG to the pipe network directly. In this way, it can resolve the energy waste problem caused by the BOG release due to excess pressure in the tanks and pipelines. In the re-condensation process with the pre-cooling device, 37.4% energy consumption can be saved compared with the one without.
Keywords:liquefied natural gas (LNG)  boil off gas (BOG)  re-condensed  direct compression  pre-cooling  
本文献已被 CNKI 等数据库收录!
点击此处可从《化工进展》浏览原始摘要信息
点击此处可从《化工进展》下载全文