The integration methodology of complete replanning and plan repairing is proposed to handle the prediction errors for energy
demands during multiperiod operational planning. Complete replanning is implemented periodically and plan repairing is triggered
during the execution interval. The plan repairing is constructed by a rule-based system because of real-time limitations.
The efficiency index of a utility pump is introduced to determine startup/shutdown of equipment without integer programming
in plan repairing. Case studies show that the proposed method is more profitable than the conventional replanning method.
The total operating costs are reduced by 0.3-9.0% compared with the conventional replanning method.