新型沉降式电站锅炉系统的技术经济分析
引用本文:徐钢,胡玥,杨勇平,许诚,宋晓娜,宋景慧.新型沉降式电站锅炉系统的技术经济分析[J].动力工程,2014(2):147-152,164.
作者姓名:徐钢  胡玥  杨勇平  许诚  宋晓娜  宋景慧
作者单位:[1]华北电力大学国家火力发电工程技术研究中心,北京102206 [2]北京信息科技大学机电实习中心,北京100192 [3]广东电网公司电力科学研究院,广州510080
基金项目:国家重点基础研究发展计划资助项目(973计划)(2009CB219801);国家自然科学基金联合基金资助项目(U1261210);高等学校学科创新引智计划资助项目(B12034);国家科技支撑计划资助项目(201IBAA04803)
摘    要:针对大容量高参数机组锅炉出现的高度增加、管道增长及阻力损失增大等问题,提出一种新型沉降式电站锅炉设计,使汽轮机平台和锅炉过热器、再热器平台在同一水平面,从而大幅度缩短主蒸汽、再热蒸汽冷段和热段管道长度,对管道长度变化带来的阻力损失、机组热经济性及发电成本的变化进行了分析.结果表明:沉降式电站锅炉的管长明显缩短,当主蒸汽、再热蒸汽冷段和热段的管道长度均减少120m时,电厂热效率提高0.18%,煤耗率降低1.044g/(kW·h),管材初投资减少约6 500万元;以年利用小时取5 294h,煤价为600元/t计算,年节煤6 093t,节约燃料成本约366万元/a,降低发电成本0.28分/(kW·h).

关 键 词:沉降式电站锅炉  管道系统  减阻优化  经济性分析

Techno-Economic Analysis of a New Settlement Power Boiler System
XU Gang,HU Yue,YANG Yongping,XUCheng,SONG Xiaona,SONG Jinghui.Techno-Economic Analysis of a New Settlement Power Boiler System[J].Power Engineering,2014(2):147-152,164.
Authors:XU Gang  HU Yue  YANG Yongping  XUCheng  SONG Xiaona  SONG Jinghui
Affiliation:1. National Thermal Power Engineering & Technology Research Center, North China Electric Power University, Beijing 102206, China; 2. Electrical and Mechanical Practice Center, Beijing Information Science & Technology University, Beijing 100192, China; 3. Electric Power Research Institute of Guangdong Power Grid Corporation, Guangzhou 510080, China)
Abstract:To solve the problems existing in large-capacity high-parameter units caused by increased height,lengthened pipeline and increased pressure loss of boiler,a new settlement boiler design was proposed,which makes the turbine platform and the boiler superheater-reheater platform on the same plane,so as to shorten the length of the main steam pipe and the cold/hot segment of reheated steam pipe.An analysis was performed on the variation of the pressure loss,the thermal economy and the cost of power generation resulted from the changes of pipe length.Results show that via the design of settlement boiler,the pipe length can be shortened significantly.When the main steam pipe,the cold segment and hot segment of reheated steam pipe are all shortened by 120 m,the thermal efficiency of the power unit will be increased by 0.18%,while the coal consumption be reduced by 1.044 g/(kW · h),and the initial investment of pipe material be reduced by 65 million RMB.Based on annual utilization hours of 5 249 h and coal price of 600 RMB/t,the annual coal consumption would be reduced by 6 093 t,meaning the fuel cost would be lowered by 3.66 million RMB/year,and the power generation cost would be reduced by 0.002 8 RMB/(kW · h).
Keywords:settlement power boiler  piping system  drag reduction optimization  economic analysis
本文献已被 CNKI 维普 等数据库收录!