引子渡水电站右岸导流洞汛期封堵质量控制
引用本文:彭文春.引子渡水电站右岸导流洞汛期封堵质量控制[J].大坝与安全,2004(2):65-67.
作者姓名:彭文春
作者单位:国家电力公司中南勘测设计研究院,湖南长沙,410014
摘    要:引子渡水电站右岸导流洞堵头封堵施工已处于汛期内,施工工期异常紧迫,为确保整个电站能按时蓄水发电,设计采用掺有MgO的膨胀混凝土,取消了接缝灌浆,同时施工准备充分,施工工艺合理,使导流洞堵头能在汛期内施工顺利完成。

关 键 词:引子渡水电站  导流洞  导流洞汛期封堵  质量控制
文章编号:1671-1092(2004)02-0065-03
修稿时间:2004年3月3日

Quality control on blocking right bank diversion tunnel during flood period
by PENG Wen-chunMid-South Design and Research Institute for Hydroelectric Projects.Quality control on blocking right bank diversion tunnel during flood period[J].Large Dam & Safety,2004(2):65-67.
Authors:by PENG Wen-chunMid-South Design and Research Institute for Hydroelectric Projects
Affiliation:by PENG Wen-chunMid-South Design and Research Institute for Hydroelectric Projects
Abstract:Blocking construction on right bank diversion-tunnel in Ynzidu hydropower station is during flood period.To ensure the project impounding and generating electricity in time,we design to adopt expanding concrete mixing MgO,calling off joint grouting,fully preparing prior construction and selecting appropriate techniques.Those measures ensured diversion blocking successfully completed during flood period.
Keywords:s:Yinzidu hydropower station  diversion tunnel  diversion tunnel blocking during flood period  quality control
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号