独脚扒杆结合单导梁法架设空心板梁施工
引用本文:胡加银. 独脚扒杆结合单导梁法架设空心板梁施工[J]. 山西建筑, 2007, 33(17): 146-147
作者姓名:胡加银
作者单位:中铁十二局集团一公司,山西,临汾,041000
摘    要:
结合工程概况,介绍了独脚扒杆结合单导梁法架设空心板梁的施工工艺原理及工艺特点、工艺流程,并详细阐述了其施工方法,指出施工质量安全注意事项,具有一定的推广价值。

关 键 词:独脚扒杆 单导梁 空心板梁 施工工艺
文章编号:1009-6825(2007)17-0146-02
修稿时间:2007-05-14

Erection construction of hollow slab beam using unipod gin pole combined with single leading-in method
HU Jia-yin. Erection construction of hollow slab beam using unipod gin pole combined with single leading-in method[J]. Shanxi Architecture, 2007, 33(17): 146-147
Authors:HU Jia-yin
Abstract:
Combined with general engineering condition, the author introduces technological principle, characteristics and process of hollow slab beam erection construction using unipod gin pole combined with single leading-in girder method, illustrates its construction method, and points out its construction quality and safety notices, which is worthy to be popularized.
Keywords:unipod gin pole   single leading-in girder   hollow slab beam   construction technology