全断面双护盾掘进机在软岩洞段施工解困中加固围岩材料的选择
引用本文:田永明.全断面双护盾掘进机在软岩洞段施工解困中加固围岩材料的选择[J].山西水利科技,2008(4).
作者姓名:田永明
作者单位:山西省水利建筑工程局,太原,030006
摘    要:全断面双护盾硬岩掘进机(简称TBM)在施工中,遇到软岩后,TBM经常出现卡机现象,这样较大程度地降低了TBM施工的效率。为了解决此类工程问题,在施工中采用了高压新型高分子注浆材料(马丽散MARITHAN),进行围岩加固施工,缩短了TBM解困的处理时间,提高了施工效率。

关 键 词:软岩  塌方  卡机  加固软岩材料选择

Selecting Meterial for Consolidating Adjoining Rock to Overcome Seizing Machine in Constructing Tunnel by TBM through Soft and Weak Stratum
TIAN Yong-ming.Selecting Meterial for Consolidating Adjoining Rock to Overcome Seizing Machine in Constructing Tunnel by TBM through Soft and Weak Stratum[J].Shanxi Hydrotechnics,2008(4).
Authors:TIAN Yong-ming
Affiliation:TIAN Yong-ming
Abstract:When soft and weak stratum is encountered in constructing tunnel by TBM,the machine-seizing phe-nomenon usually occurs.It results in decreasing construction efficiency in great degrees.In order to solve this problem,a new high-pressure and high-macromolecular grouting meterial,MARITHAN is used in construction to consolidate adjoining rock of tunnel.Therefore,the treatment time to solve maching-seizing is shortened,and the construction efficiency is raised.
Keywords:soft and weak stratum collapse machine-seizing selecting meterial to consolidate soft and weak stratum