深海沉管隧道基础水下沉降监测技术
引用本文:王延宁,蒋斌松,张强,陈运涛.深海沉管隧道基础水下沉降监测技术[J].长江科学院院报,2018,35(3):116-121.
作者姓名:王延宁  蒋斌松  张强  陈运涛
作者单位:1.中国矿业大学 深部岩土力学与地下工程国家重点实验室,江苏 徐州 221116;2.中交天津港湾工程研究院有限公司,天津 300222
基金项目:国家自然科学基金项目,国家科技支撑计划课题
摘    要:为消除管节间差异沉降,港珠澳大桥岛—隧过渡段沉管基础采用挤密砂桩+堆载预压的地基处理方式。详细介绍了采用液体压差式沉降仪监测沉管隧道基础沉降的应用技术,并获得了较好的复合地基沉降数据。采用多种技术手段保证仪器埋设成功率,包括作业时机选择、导线接头及导线保护等。对试验结果进行分析,结果表明该技术运行稳定性高、数据误码率低、不易受风浪及施工干扰,可实现对沉管基础的连续稳定无线监测。

关 键 词:港珠澳大桥沉管隧道  挤密砂桩  堆载预压  沉降计算  原位测试  
收稿时间:2017-09-18

An Underwater Settlement Monitoring Technique for Deep-sea Immersed Tunnel Foundation
WANG Yan-ning,JIANG Bin-song,ZHANG Qiang,CHEN Yun-tao.An Underwater Settlement Monitoring Technique for Deep-sea Immersed Tunnel Foundation[J].Journal of Yangtze River Scientific Research Institute,2018,35(3):116-121.
Authors:WANG Yan-ning  JIANG Bin-song  ZHANG Qiang  CHEN Yun-tao
Affiliation:1.State Key Laboratory for Geomechanics and Deep Underground Engineering, China University of Miningand Technology, Xuzhou 221116, China; 2.Tianjin Port Engineering Institute Co., Ltd. of CCCC FirstHarbor Engineering Co., Ltd., Tianjin 300222, China
Abstract:The island-tunnel segment of Hong Kong-Zhuhai-Macau Bridge is featured with deep soft soil under the immersed tube foundation. Sand compaction pile together with preloading was adopted to eliminate the differential settlement between joint parts. In this paper,the technique of monitoring tube foundation settlement by liquid pres-sure settlement sensor is introduced in details. Satisfactory settlement data was obtained. A variety of technical ap-proaches,including the timing of operations,protection of wire connectors and wire,were employed to improve the success rate of equipment burying. Test results showed that the technique could perform continuous stable wireless monitoring as it is of high stability,low error rate,and is less susceptible to wind and waves and construction inter-ferences. Therefore it could realize the continuous and stable wireless monitoring of the foundation. The study is ex-pected to provide reference for the monitoring of composite foundation under deep water conditions.
Keywords:immersed tube tunnel of Hong Kong-Zhuhai-Macau Bridge  sand compaction pile  preloading  settlement calculation  in situ test  