200MW汽轮机疏水系统的改进
引用本文:许文辉,戴木强.200MW汽轮机疏水系统的改进[J].发电设备,2009,23(4):262-265.
作者姓名:许文辉  戴木强
作者单位:茂名热电厂,茂名,525011
摘    要:针对汽轮机启、停过程中发生的汽缸上、下壁温差大的故障进行了分析,指出其原因是疏水系统存在缺陷,因而提出了疏水系统的改进方案和操作的建议。实施改造后保证了汽轮机的安全运行,启动过程中汽缸上、下壁温差保持在40K以下。

关 键 词:汽轮机  汽缸壁温差  疏水系统

Retrofit on Drainage System of 200MW Turbines
XU Wen-hui,DAI Mu-qiang.Retrofit on Drainage System of 200MW Turbines[J].Power Equipment,2009,23(4):262-265.
Authors:XU Wen-hui  DAI Mu-qiang
Affiliation:XU Wen-hui,DAI Mu-qiang Maoming Thermal Power Plant,Maoming 525011,China
Abstract:The failure of too large temperature difference between upper and lower wall of turbine cylinder during start/stop period of the turbine was analyzed,which was found to be caused by imperfect structure of the drainage system,for which retrofit scheme and manipulation suggestions were proposed.Actual temperature difference between the upper and lower wall is now below 40 K during start up period after retrofit,resulting in safety operation of the turbine.
Keywords:steam turbine  temperature difference between cylinder walls  water drain system  