摘 要: | 顶管施工是一项系统性很强的复杂工程,在施工的每个环节都存在一定的风险。本文主要针对顶管施工过程中的地面沉降风险进行分析,总结了一些关于顶管施工过程中地面沉降风险控制的方法,可为类似顶管工程施工的地面沉降风险控制提供参考。
|
关 键 词: | 顶管 地面沉降 原因分析 控制目标 控制措施 信息化施工 |
Risk control of land subsidence in the process of pipe jacking construction |
| |
Abstract: | Pipe jacking is a very complicated system construction, and there are certain risks in each link of construction. Risks of land subsidence in the process of pipe jacking construction are analyzed in this article. Some risk control methods of land subsidence during pipe jacking construction are summarized, which could provide some references for land subsidence risk control of similar pipe jacking construction. |
| |
Keywords: | pipe jacking land subsidence reason analysis control target control measures informationization construction |