摘    要:
根据昌山电站的实际情况,进行闸坝工作门方案的比选,确定采用液压翻板闸门。分析液压翻板闸门的特点,提出设计中应采取的安全措施,和施工、运行中一些安全对策。

关 键 词:翻板闸门 液压启闭机 设计 安全对策 昌山水电站
文章编号:1003-1510(2002)01-0034-03

Lock dam work gate scheme design of the Changshan hydropower station pivotal project
LIU Xi_long,HUANG Jun,XIAO Duan_long,CHEN Fu_rong. Lock dam work gate scheme design of the Changshan hydropower station pivotal project[J]. Gx Water Resources & Hydropower Engineering, 2002, 0(1): 34-36,39
Authors:LIU Xi_long  HUANG Jun  XIAO Duan_long  CHEN Fu_rong
Abstract:
According to the actual situation of the Changshan hydropower station, the authors compared the lock dam work gate schemes and determined using hydraulic flap gate. The gate features were analyzed and some safety countermeasures in design, construction and operation were expounded.
Keywords:work gate  scheme  flap gate  hydraulic hoist  design  safety countermeasure