钢箱连续梁桥大节段吊装施工设计计算分析
引用本文:林桢楷.钢箱连续梁桥大节段吊装施工设计计算分析[J].山西建筑,2014(18):220-221.
作者姓名:林桢楷
作者单位:广东省公路勘察规划设计院股份有限公司,广东广州510640
摘    要:以在建佛陈大桥为工程背景,从大节段吊装施工阶段主梁受力、变形情况,成桥状态下主梁关键部位上下缘应力大小、成桥位移,钢箱梁制造线形计算等几方面内容与常规小节段悬拼施工进行对比分析,从设计计算方面论证了钢箱连续梁桥中跨大节段整体吊装施工方案的可行性,分析结论对同类桥型设计具有一定参考意义。

关 键 词:钢箱连续梁  大节段吊装  施工方案  设计

Calculation analysis on large-section hoisting construction design of steel-box continuous beam
LIN Zhen-kai.Calculation analysis on large-section hoisting construction design of steel-box continuous beam[J].Shanxi Architecture,2014(18):220-221.
Authors:LIN Zhen-kai
Affiliation:LIN Zhen-kai
Abstract:Taking in-building Fochen bridge as the engineering background, the article compares major beam stress and deformation conditions at large-section hoisting stage, upper-lower beam stress, completed bridge displacement and steel-box-girder linear calculation to conventional small-section cantilever construction, and discusses the feasibility of large-section hosting construction scheme of steel-box-beam bridge from aspects of design and computation. Thus, the analysis conclusions will have certain referring meaning for similar bridge design.
Keywords:steel-box continuous beam  large-section hoisting  construction scheme  design