考虑电网多元风险的输电断面动态增容调度分配方案
引用本文:钱海,王奇,陈翔宇,胡军.考虑电网多元风险的输电断面动态增容调度分配方案[J].中国电力,2015,48(10):60-64.
作者姓名:钱海  王奇  陈翔宇  胡军
作者单位:1. 中国南方电网超高压输电公司检修试验中心,广东 广州 510663;2. 电力系统及发电设备控制和仿真国家重点实验室清华大学电机系,北京 100084
基金项目:国家高技术研究发展计划(863计划资助)项目(2012AA050209)
摘    要:针对目前电网输电断面增容容量分配决策的相关问题,提出一种考虑电网多元风险的输电断面动态增容调度分配方案优化模型。该模型考虑了电网面临的多元风险约束,包括设备健康风险、气象风险和系统异常风险。其中,断面内通道的容量裕量限额是通过三大定容设备——变压器、断路器以及输电线路的动态增容计算模型得到的。所提出的考虑电网多元风险的输电断面动态增容调度分配方案,可以较好地平衡大电网电能输送中的经济性和安全性问题,为解决输电断面内动态增容分配提出了一个新的解决思路和技术方案。

关 键 词:输电断面  负荷分配  动态增容  多元风险  状态评估  优化模型  
收稿时间:2015-07-10

Distribution Scheme for Dynamic Capacity-Increase of the Transmission Section with Considering the Multi-risk of Power Grid
QIAN Hai,WANG Qi,CHEN Xiangyu,HU Jun.Distribution Scheme for Dynamic Capacity-Increase of the Transmission Section with Considering the Multi-risk of Power Grid[J].Electric Power,2015,48(10):60-64.
Authors:QIAN Hai  WANG Qi  CHEN Xiangyu  HU Jun
Affiliation:1. M&T Center, EHV Power Transmission Company, China Southern Power Grid, Guangzhou 510663, China; 2. State Key Lab of Control and Simulation of Power Systems and Generation Equipment Dept. of Electrical Engineering, Tsinghua University, Beijing 100084, China
Abstract:In view of the decision-making issues related to the distribution of dynamic capacity-increase of transmission section, a distribution scheme optimization model is proposed in this paper for transmission section dynamic capacity-increase with consideration of the multi-risk of power grid. The model developed in this paper takes multi-risk constraints into consideration, which include health risk of power equipment, weather risk and system anomaly risk. The capacity limits of the transformer, breaker and transmission line are determined by capacity-increase calculation model. The proposed distribution scheme can balance the economy and security in power transmission of large power grids and provide a possible solution and technical scheme for dynamic capacity-increase distribution of transmission section. This work is supported by National High Technology Research and Development Program of China (863 Program) (No. 2012AA050209).
Keywords:transmission section  load distribution  dynamic capacity-increase  multi-risk  status evaluation  optimization model  
点击此处可从《中国电力》浏览原始摘要信息