首页 | 本学科首页   官方微博 | 高级检索  
     

苏只水电站电气主接线选择
引用本文:王兰.苏只水电站电气主接线选择[J].西北水电,2008(2):51-52.
作者姓名:王兰
作者单位:中国水电顾问集团西北勘测设计研究院,西安710065
摘    要:苏只水电站装机3台,单机容量为75MW,出线110kV和330kV两级电压,经过对该两级电压的联络方案的技术、经济比较,选定苏只电气主接线。

关 键 词:电气主接线  联络变压器  二三绕组变压器  苏只水电站

Selection of Main Electric Connection for Suzhi HPP
WANG Lan.Selection of Main Electric Connection for Suzhi HPP[J].Northwest Water Power,2008(2):51-52.
Authors:WANG Lan
Affiliation:WANG Lan (Northwest Hydro Consulting Engineers, CHECC, Xi'an 710065)
Abstract:The Suzhi HPP has 3 units each with an installed capacity of 75 MW, and the outgoing lines are at 2 voltage grades of 110 kV and 330 kV. Through technical and economic comparisons of the above 2 voltage grades, the main electric connection for Suzhi HPP is determined.
Keywords:main electric connection  interconnecting transformer  three- winding transformer  Suzhi HPP
本文献已被 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号