云南某铜尾矿库不同堆坝速率稳定性分析
引用本文:张卫中,康钦容,曹冠森,张电吉.云南某铜尾矿库不同堆坝速率稳定性分析[J].金属矿山,2016,45(11):39-42.
作者姓名:张卫中  康钦容  曹冠森  张电吉
作者单位:1.武汉工程大学资源与土木工程学院,湖北 武汉430073;2.湖北兴发化工集团股份有限公司,湖北 宜昌 443007;3.重庆大学资源及环境科学学院,重庆 400030
基金项目:国家自然基金项目(51104176;51474159),武汉工程大学科学基金项目(K201320;K201321),国家磷资源开发利用工程技术研究中心开放基金项目(2012国磷k001)
摘    要:根据云南某铜尾矿库地勘和设计施工资料,按照尾矿库比例和现场堆坝形式,进行了大型堆坝模型试验,通过对三级子坝采样并进行颗粒级配分析,获取了模型尾矿库内颗粒级配分布。根据得到的颗粒分布确定组成尾矿库的2类尾矿样,对其采用常规土工试验获得常规土力学参数。在专用岩土数值模拟软件Geo-slope中建模并代入2种尾矿土物理力学参数,进行正常工况下的稳定性计算,得到3种堆积坝高下不同筑坝速度的安全系数(其中,4级子坝在堆坝速度5 m/a情况下,安全系数为2.173,为最大值;10级子坝在堆坝速度15 m/a情况下,安全系数为1.252,为最小值)。结果表明:在相同堆积速率下尾矿库越高安全系数越低;随着筑坝速率提高,相同坝高尾矿库坝体稳定性下降。在尾矿库设计建设时,有必要考虑尾矿库堆坝速率进行稳定性分析。

关 键 词:尾矿库  筑坝速率  模型试验  数值模拟  安全系数

Stability Analysis on a Copper Tailing Dam under Different Damming Rate in Yunnan
Zhang Weizhong,Kang Qinrong,Cao Guansen,Zhang Dianji.Stability Analysis on a Copper Tailing Dam under Different Damming Rate in Yunnan[J].Metal Mine,2016,45(11):39-42.
Authors:Zhang Weizhong  Kang Qinrong  Cao Guansen  Zhang Dianji
Affiliation:1.School of Resources and Civil Engineering,Wuhan Institute of Technology,Wuhan 430070,China;2.Hubei Xingfa Chemicals Group Co.,Ltd.,Yichang 443000,China;3.College of Resources and Environmental Science,Chongqing University,Chongqing 400030,China;
Abstract:According to the geological exploration and design materials of Yunnan copper tailings,large dam model are tested on the basis of the proportion of the tailings dam and the on-site damming form. Through analysis on the grain size distri-bution of samplings from tertiary sub-dam tailings, the regularity of grain size distribution in the tailing dam model are ob-tained. According to the regularity,two types of tailing sample are classified and tested by the conventional geotechnical tests to achieve the conventional soil mechanics parameters. With the use of the geotechnical numerical simulation software Geo-slope, two kinds of tailings soil physical and mechanical parameters are substituted into the model to calculate the stability under the normal working conditions. The safety coefficient under three damming heights and different damming speed kinds of stacking dam against different speed of dam are calculated out ( Among them, the maximum safety factor for the level 4 sub-dam is 2. 173 when the damming speed is 5 m/a;the minimum safety factor for level 10 sub-dam is 1. 252 when the deposition rate is 15 m/a) . The results show that under the same deposition rate,the higher the tailings,the lower the safety factor;As the dam-ming rate increase,the stability of tailing dam with the same height declines. It is necessary to make stability analysis by con-sidering the damming rate of the tailings dam.
Keywords:Tailings  Damming rate  Model test  Numerical simulation  Safety factor
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《金属矿山》浏览原始摘要信息
点击此处可从《金属矿山》下载全文