黄河柴家峡水电站施工截流思考
引用本文:张淑琴.黄河柴家峡水电站施工截流思考[J].西北水电,2006(4):50-52.
作者姓名:张淑琴
作者单位:中国水电顾问集团西北勘测设计研究院,西安,710065
摘    要:黄河柴家峡截流流量主要受控于上游已建梯级电站群。2005年黄河上游水量偏丰,9~11月柴家峡坝址河道流量超过多年平均流量1 050 m3/s,截流戗堤预进占的实际流量1 700 m3/s,龙口合龙进占流量1 200~1 700m3/s,仅次于黄河三门峡截流流量2 000 m3/s。如此大流量截流成功,值得总结和思考。

关 键 词:柴家峡水电站  截流  思考
文章编号:1006-2610(2006)03-0050-03
收稿时间:2006-08-18
修稿时间:2006年8月18日

On river closure of Chaijiaxia hydropower project
ZHANG Shu-qin.On river closure of Chaijiaxia hydropower project[J].Northwest Water Power,2006(4):50-52.
Authors:ZHANG Shu-qin
Abstract:The discharge for river closure of Chaijiaxia hydropower project is mainly controlled by the existing cascade hydropower stations on upstream Yellow River.In 2005,the water quantity of upstream Yellow River was abundant,and the river discharge at damsite was more than mean annual discharge of 1 050 m~3/s.The actual discharge for pre-embankment of the banquette was 1 700 m~3/s,and the discharge at closure gap was 1 200~1 700 m~3/s that was merely next to the closure discharge of 2 000 m~3/s for Sanmenxia hydropower station on Yellow River.It is worth thinking and summing-up on successful completion of river closure.
Keywords:Chaijiaxia  river closure  consideration