大容量火电机组启动/备用电源引接方式分析
引用本文:王予英.大容量火电机组启动/备用电源引接方式分析[J].中国电力,2007,40(2):43-45.
作者姓名:王予英
作者单位:中国电力工程顾问集团公司,北京,100011
摘    要:近年来,随着电力系统体制改革厂网分开,当由系统就近的220kV(110kV)变电站引接启动/备用电源时,由于交纳容量电费,使得机组启动/备用变压器运行费用增加,引起机组启动/备用电源引接方式发生了较大变化。论述了电厂送出为500kV(330kV)电压时,电厂500kV(330kV)配电装置降压引接启动/备用电源方案的可行性,并就一些工程的应用情况提出意见。

关 键 词:大容量  火电机组  启动/备用电源  引接方式
文章编号:1004-9649(2007)02-0043-03
修稿时间:2006-10-13

Study on connection of high voltage auxiliary start-up/standby power source for large capacity fossil fuel power units
WANG Yu-ying.Study on connection of high voltage auxiliary start-up/standby power source for large capacity fossil fuel power units[J].Electric Power,2007,40(2):43-45.
Authors:WANG Yu-ying
Affiliation:China Power Engineering Consulting Group Corporation, Beijing 100011,China
Abstract:Recent years, along with the reform of electric power system, the power plants were separated from power network. When high voltage auxiliary start-up/standby power source is supplied by neighboring 220 kV (110 kV) substation, the running expenses of start-up/standby transformers were largely increased due to paying the transformer's capacity expenses to network. As a result, the connection scheme of start-up/standby power source has a biggish changing. The article discusses the feasibility of the connection which high voltage auxiliary start-up/standby power source is supplied by 500 kV(300 kV) bus of the power plant, when transmission voltage of the power plant is 500 kV(300 kV), and some ideas for practical engineering application are proposed.
Keywords:large capacity  fossil fuel power unit  start-up/standby power source  connection