摘    要:依托大连某桥隧建设工程,分别采用导洞法、单侧壁导坑法和双侧壁导坑法模拟大断面公路隧道的开挖过程,详细分析了隧道开挖支护后围岩的位移场与应力场的变化,通过对比研究,得出双侧壁导坑法开挖过程位移变化最小,受力均匀,更有利于维持围岩稳定性的结论。

关 键 词:大断面  开挖方法  数值模拟  双侧壁导坑法

On numeric analysis of excavation methods of large-section road tunnels
ZHENG Hui.On numeric analysis of excavation methods of large-section road tunnels[J].Shanxi Architecture,2014(15):168-169.
Authors:ZHENG Hui
Affiliation:ZHENG Hui ( Dalian Radio and Television University, Dalian 116021, China)
Abstract:Referring to some bridge tunnel construction project in Dalian, the paper adopts the pilot-tunneling method, the side wall heading method, and the twin-side heading method to simulate the excavation process of the large-section road tunnels, analyzes the changes the displacement field and stress field in the surrounding rock after the excavation support of tunnels, and concludes the twin-side heading method has the smallest displacement changes, even stress and it can bitterly maintain the stability of the surrounding rock.
Keywords:arge-section  excavation method  numeric simulation  twin-side heading method