三山岛金矿采场充填脱水工艺改进措施
引用本文:颜丙乾,杨鹏,吕文生.三山岛金矿采场充填脱水工艺改进措施[J].金属矿山,2015,44(3):48-52.
作者姓名:颜丙乾  杨鹏  吕文生
作者单位:1.北京科技大学土木与环境工程学院,北京 100083;2.金属矿山高效开采与安全教育部重点实验室,北京 100083;3.北京市信息服务工程重点实验室,北京 100101
基金项目:* “十二五”国家科技支撑计划项目(编号:2012BAB08B01)。
摘    要:采场充填脱水效果对充填体初凝时间及其短期和长期强度产生较大影响,三山岛金矿采用溢流管溢流脱水和充填挡墙的土工布渗透脱水,脱水效率不能满足现场工作要求。为此,在充填脱水理论研究的基础上,分析了影响充填脱水速度的主要因素,提出了多项充填脱水改进措施。增设竖直或倾斜的脱水管,更有效地排出充填采场中的重力水,同时避免充填料浆中细粒级颗粒堵塞脱水管。改进充填挡墙设计和滤水布的选取,避免细粒级颗粒短时间内聚集在滤水布附近,影响渗透脱水效果。设计充填管道滤水器,在充填料浆进入采空区前,过滤充填料浆中的部分自由水,提高了充填采场中料浆的浓度,减小了采场充填脱水工作量。改变矿山简单脱水方式,进一步提高采场充填脱水效率,避免影响下一步开采工作的顺利开展。

关 键 词:充填体  采场充填脱水  脱水管  渗透脱水  充填体强度  

Improvement Measures of Stope Filling Dewatering Process in Sanshandao Gold Mine
Yan Bingqian,Yang Peng,Lu Wensheng.Improvement Measures of Stope Filling Dewatering Process in Sanshandao Gold Mine[J].Metal Mine,2015,44(3):48-52.
Authors:Yan Bingqian  Yang Peng  Lu Wensheng
Affiliation:1.School of Civil and Environmental Engineering,University of Science and Technology Beijing,Beijing 100083,China;2.State Key Laboratory of High-efficient Mining and Safety of Metal Mines,Ministry of Education,Beijing 100083,China;3.Beijing Key Laboratory of Information Service Engineering,Beijing 100101,China
Abstract:The dewatering of stope filling has a greater impact on the initial setting time of the filling body and its short-term and long-term strength.The overflow dewatering was used in Sanshandao Gold Mine by overflow tube,and penetration dewatering was used by filling retaining geotextile,but the dewatering efficiency can not meet the requirements of field work.The main influence factors of the filling dewatering rate was analyzed on the basis of theoretical research on the filling dewatering,and many improvement measures of filling dewatering are put forward.Additional vertical or inclined dewatering tubes can be used to discharge the filling gravity water more efficiently,meanwhile avoid dewatering tube clogged by the fine-sized particles in filling slurry.The improved design of filling retaining wall and selection of treatment cloth can avoid the fine-sized particles gathered near the water treatment cloth in short time which can affect penetration dewatering.The water filter of filling tube was designed to filter part of free water in filling slurry before filling the slurry into the stope area,improve concentration of filling slurry,and reduce workload of stope filling dewatering.Changing simple dewatering way to further improve the efficiency of the stope filling dewatering,can avoid from affecting the development of the next mining work.
Keywords:Filling body  Dewatering of stope filling  Dewatering tube  Penetration dewatering  Strength of the filling body