无粘结环锚预应力衬砌锚具槽布置方式对比研究
引用本文:曹瑞琅,王玉杰,皮进,郑理峰,刘立鹏.无粘结环锚预应力衬砌锚具槽布置方式对比研究[J].水利水电技术,2017,48(7):59-63.
作者姓名:曹瑞琅  王玉杰  皮进  郑理峰  刘立鹏
作者单位:( 1.中国水利水电科学研究院流域水循环模拟与调控国家重点实验室,北京100038; 2.北京航空航天大学交通科学与工程学院, 北京100091)
摘    要:无粘结环锚预应力衬砌锚具槽是整个预应力衬砌受力的关键部位,其位置的选择对于整个预应力衬砌受力和安全而言至关重要。结合引松供水工程有压输水隧洞无粘结预应力衬砌结构,采用等效荷载法和实体建模相结合的方法进行Flac3D三维建模,对锚具槽单排和双排布置时的衬砌关键部位受力情况进行了分析。计算结果表明:(1)无粘结环锚预应力衬砌的下半环因锚具槽的影响,会存在局部预应力缺失和分布不均,而单排锚具槽布置能减小衬砌预应力的不均匀性。(2)锚具槽及附近区域是预应力衬砌的薄弱区,衬砌拉应力区主要分布在锚具槽环向的临空面附近,衬砌受压最大区域分布在相邻锚具槽之间。(3)双排锚具槽布置型式抗超载能力优于单排锚具槽布置型式。

关 键 词:预应力衬砌  无粘结环锚  锚具槽  有压隧洞  数值计算  
收稿时间:2016-08-15

Comparative study on layout patterns of anchorage slots for pre-stressed lining with unbonded circular anchored tendons
CAO Ruilang,WANG Yujie,PI Jin,ZHENG Lifeng,LIU Lipeng.Comparative study on layout patterns of anchorage slots for pre-stressed lining with unbonded circular anchored tendons[J].Water Resources and Hydropower Engineering,2017,48(7):59-63.
Authors:CAO Ruilang  WANG Yujie  PI Jin  ZHENG Lifeng  LIU Lipeng
Affiliation:(1.China State key Laboratory of Simulation and Regulation of Water Cycle in River Basin, China Institute of Water Resources and Hydropower Research, Beijing100038, China;2.Beihang University,School of Transportation Science and Engineering, Beijing100091, China)
Abstract:The slots of pre-stressed lining anchorage with unbonded circular anchored tendons are the key forced parts for entire pre-stressed lining, and then the selection of their locations is quite important for the forced status and safety of entire pre-stressed lining. Combined with the unbounded pre-stressed lining structure of the pressure water conveyance tunnel for Songhuajiang River Diversion Water Supply Project, the forced statuses of the key parts of the lining with single-row layout and double-row layout of anchorage slots are analyzed with Flac3D modeling carried out by combining equivalent load method with solid modeling method. The calculation result shows that: (1) the absence and ununiform distribution of the local pre-stress are there at the lower half-ring of the pre-stressed lining with unbonded circular anchored tendons due to the influence from anchorage slot, whereas, the ununiformity of the lining pre-stress can be reduced by the single-row layout of the anchorage slots; (2) both the anchorage slots and the areas near them are the weak locations for the pre-stressed lining and the lining tensile stress areas are mainly distributed near the circular free face of the anchorage slot, while the maximum forced areas of lining are distributed in between adjacent anchorage slots; (3) the anti-overload capacity of the double-row layout of anchorage slots is better than that of the single-row layout of anchorage slots.
Keywords:pre-stressed lining  unbonded circular anchored tendons  anchorage slot  pressure tunnel  numerical calculation    