浅析不锈钢覆面的先贴法施工
引用本文:黄振. 浅析不锈钢覆面的先贴法施工[J]. 中国核电, 2011, 0(2): 125-129
作者姓名:黄振
作者单位:中国核工业第二二建设有限公司;
摘    要:为减少不锈钢覆面的现场施工工作量,有效地缩短整个工程项目的建造周期,不锈钢覆面施工采用分片分段在车间进行预制,现场进行拼装的施工方法,有效地缩短了不锈钢覆面在整个土建工程施工关键路径中的必需作业时间,加快了工程项目关键路径的建造进度,不锈钢覆面的先贴法施工可进一步推广。

关 键 词:先贴法  车间预制  现场拼装  分层浇筑

Brief analysis of priority assembly construction method for stainless steel liner
HUANG Zhen. Brief analysis of priority assembly construction method for stainless steel liner[J]. China Nuclear Power, 2011, 0(2): 125-129
Authors:HUANG Zhen
Affiliation:HUANG Zhen(China Nuclear Industry 22nd Construction Co.,Ltd.,Haiyan of Zhejiang Prov.314300,China)
Abstract:In order to reduce the field construction workload of stainless steel liner and effectively shorten the construction period of the entire project,shop pre-fabrication(per blocks,sections) and field assembly method is adopted in the construction of stainless steel liner,which effectively shorten the necessary operation time in the critical path of the entire civil project construction,and speed up the construction progress of the critical path.The priority assembly construction method of stainless steel line...
Keywords:priority assembly  shop pre-fabrication  field assembly  concreting in lifts  