摘    要:本文回顾了大河口电站导流隧洞及过水围堰快速施工过程。说明加速电站建设只有一开始就抓住工程特点,采取相应措施,才能获得较好效果。

关 键 词:导流隧洞  过水围堰  水电站  工程施工

Rapid Construction for Diversion Tunnel and Overtopped Cofferdam at Dahekou Hydropower Station
Chen Yihai.Rapid Construction for Diversion Tunnel and Overtopped Cofferdam at Dahekou Hydropower Station[J].Sichuan Water Power,1995,14(1):66-68.
Authors:Chen Yihai
Affiliation:The Eighth Hydroelectric Engineering Construction Bureau
Abstract:Rapid construction for diversion tunnel and overtopped cofferdam at Dahekou hydropower stationare reviewed in this paper. It is proved that for rapid construction of a hydropower project,the engineeringfeatures must be known and corresponding measures must taken at the beginnig.
Keywords:diversion tunnel cofferdam rapid construction