探讨千米深立井快速施工技术
引用本文:黄寿强.探讨千米深立井快速施工技术[J].矿业工程,2016(1):3-6.
作者姓名:黄寿强
作者单位:湖南涟邵建设工程 集团 有限责任公司,湖南 娄底,417000
摘    要:介绍了贵州武陵矿业李家湾锰矿千米主、副立井工程施工,该工程采用立井机械化配套作业线、正规循环滚班制作业方式快速施工,主井基岩段连续8个月成井901.95m,平均月成井118.2m,最高月成井151.9m,创国内立井井筒快速施工新纪录。

关 键 词:千米深井  机械化配套  正规循环  快速施工

Discussion on Rapid Construction Technology of Kilometer-depth Shaft
Abstract:The paper introduces the construction of kilometer-depth main and assistant shaft project of Lijiawan manganese ore of Guizhou Wuling Mining. This project uses shaft mechanization matching operating line, and standard cycling shifts operation methods for rapid construction. In consecutive 8 months, the shaft forming of basement section of main shaft is 901. 95m, average 118. 2m per month, and maxim shaft-forming in one month is 151. 9m. This is a new record for rapid construction of shaft in China.
Keywords:kilometer-depth shaft  mechanization matching  standard cycling  rapid construction