巷道滞后注浆加固与滞后时间分析
引用本文:贺永年,张农.巷道滞后注浆加固与滞后时间分析[J].煤炭学报,1996,21(3):240-244.
作者姓名:贺永年  张农
作者单位:中国矿业大学
摘    要:根据巷道围岩超过强度峰值后的变形是其强度不断降低的平衡过程,分析了滞后注浆巷道稳定技术的原理考虑实现新平衡及其所需的时间提前量,结合巷道变形(或破碎圈)发展规律的经验关系,给出注浆加固巷道稳定技术的滞后时间参数确定方法其结果在经验的最佳滞后时间范围上限,较国外方法有更合理之处

关 键 词:注浆加固  稳定分析  滞后时间

ANALYSIS OF DELAYED GROUTING OF ROADWAY AND LAGGING TIME
He Yongnian,Zhang Nong,Yang Mijia,Dai Biaobing.ANALYSIS OF DELAYED GROUTING OF ROADWAY AND LAGGING TIME[J].Journal of China Coal Society,1996,21(3):240-244.
Authors:He Yongnian  Zhang Nong  Yang Mijia  Dai Biaobing
Affiliation:China University of Mining and Technology
Abstract:The principle for stabilizing the roadway by delayed grouting is described based on the balance process of the rocks of roadway after the peak strength.A method for determination of the parameter of the lagging time,is given by taking into consideration of new balance and the lead time required.The calculated data is within the upper limit of the optimal lagging time,which is more reasonable than the method used abroad.
Keywords:consolidation of rock by grouting  stability analysis  lagging time  