松树南沟矿区边坡岩体质量评价与边坡稳定性分析
引用本文:王伟,胡斌,甘露,欧光劲.松树南沟矿区边坡岩体质量评价与边坡稳定性分析[J].金属矿山,2014,43(5):45-49.
作者姓名:王伟  胡斌  甘露  欧光劲
作者单位:1.中国地质大学(武汉)工程学院,湖北 武汉 430074;2.成都建筑材料工业设计研究院有限公司,四川 成都 610011;3.四川金顶(集团)股份有限公司,四川 峨眉山 614224
基金项目:* 国家重点基础研究发展计划(973计划)项目(编号:2011CB710604),国家自然科学基金面上项目(编号:41172281),中央高校基本科研业务费专项(编号:CUGL100413,CUG090104)。
摘    要:为了评价松树南沟矿区边坡岩体开挖稳定性情况,指导矿山的安全施工,以结构面测量与工程勘察为基础,分析边坡岩体结构面的分布及岩体结构特征,得到对边坡稳定起控制作用的优势结构面。利用结构面三维网络模拟技术,对上述优势结构面进行计算机模拟,建立结构面网络模型,再现岩体结构。分别沿平行和垂直各测线走向方向切割网络模型,发现岩体部分区域被结构面切割严重,为形成小规模的可动块体提供了有利条件。运用分形理论计算了各切面的分形维数,计算得出边坡岩体处于一般或差的状态;借助有限差分软件FLAC3D,计算开挖后边坡岩体的稳定性情况,结果表明:由于开挖卸荷局部边坡台阶处出现了较大的位移和塑性区,可能出现崩塌、滑移破坏,与质量评价结果一致,建议适当放缓该区域台阶坡面角。


Quality Evaluation of Rock Mass and Stability Analysis of Slope in Songshunangou Mining Area
Wang Wei,Hu Bin,Gan Lu,Ou Guangjin.Quality Evaluation of Rock Mass and Stability Analysis of Slope in Songshunangou Mining Area[J].Metal Mine,2014,43(5):45-49.
Authors:Wang Wei  Hu Bin  Gan Lu  Ou Guangjin
Affiliation:1.Faculty of Engineering,China University of Geosciences,Wuhan 430074,China;2.Chengdu Design & Research Institute of Building Materials Industry Co.,Ltd.,Chengdu 610011,China;3.Sichuan Golden Summit (Group) Co.,Ltd.,Emeishan 614224,China;
Abstract:In order to evaluate the stability of slope rock mass after excavation and to guide construction safety,based on the discontinuity measurement and engineering survey,the characteristics of discontinuity distribution and rock mass′ structure in Songshunangou Mining Area were analyzed,thus obtaining the advantage discontinuity which controls the slope stability.Three-dimensional network simulation technology was used to make simulation on the advantage discontinuity above and establish the network model to represent the rock-mass′s structure.The network model was cut along each measuring line in parallel or perpendicular direction.It is found that rock-mass were cut seriously by the discontinuity,which provides favorable conditions for the formation of small-scale movable ore blocks.The fractal dimension of each section was calculated by the fractal geometry theory,finding that rock mass is in general or poor state.With the aid of the finite difference software FLAC3D,the stability of rock mass after excavation was calculated.The results showed that due to the excavation and unloading,larger displacement and plastic zone in some parts of slope were generated,possibly resulting in collapse and slippage.It fits with the quality assessment,so reasonably lowering the step slope angle is recommended.