四川会东某铅锌矿石选矿工艺优化研究
引用本文:黄和平,罗仙平,翁存建,陈迪胜,孙洪林,周华荣.四川会东某铅锌矿石选矿工艺优化研究[J].金属矿山,2017,46(7):101-109.
作者姓名:黄和平  罗仙平  翁存建  陈迪胜  孙洪林  周华荣
作者单位:1.江西理工大学资源与环境工程学院,江西 赣州 341000;2.西部矿业科技有限公司,青海 西宁 810006;3.青海省高原矿物加工工程与综合利用重点实验室,青海 西宁 810006;4.青海省有色矿产资源工程技术研究中心,青海 西宁 810006;5.四川会东铅锌矿,四川 会东615205
基金项目:国家自然科学基金项目,青海省企业研究转化与产业化专项,青海省重点实验室发展专项
摘    要:四川会东某高泥铅锌矿石主要有价组分铅、锌、银含量分别为1.01%、6.30%、34.89 g/t,铅矿物以方铅矿为主,锌矿物以闪锌矿为主。由于现场浮铅时抑锌效果不理想,即使浮选工艺流程冗长,但铅、锌精矿指标仍不理想。试验引进新型、高效抑制剂XKY-02配合硫酸锌抑锌浮铅,再活化选锌,在磨矿细度为-200目占80%的情况下,采用1粗2精1扫浮选选铅、1粗1精1扫浮选选锌、中矿顺序返回流程处理矿石,获得了铅品位为55.77%、银品位为571.72 g/t、含锌6.70%、铅回收率为71.05%、银回收率为21.17%的铅精矿,以及锌品位为56.06%、银品位为244.87 g/t、含铅1.04%、锌回收率为92.59%、银回收率为72.99%的锌精矿。与现场工艺相比,铅、锌选矿工艺段数明显减少,但精矿指标明显改善。

关 键 词:铅锌矿  浮选  抑制剂XKY-02

Technological Optimization on Mineral Processing of a Lead-Zinc Sulphide Ore in Huidong County,Sichuan Province
Huang Heping,Luo Xianping,Weng Cunjian,Chen Dishen,Sun Honglin,Zhou Huarong.Technological Optimization on Mineral Processing of a Lead-Zinc Sulphide Ore in Huidong County,Sichuan Province[J].Metal Mine,2017,46(7):101-109.
Authors:Huang Heping  Luo Xianping  Weng Cunjian  Chen Dishen  Sun Honglin  Zhou Huarong
Affiliation:1.School of Resources and Environmental Engineering,Jiangxi University of Science and Technology,Ganzhou 341000,China;2.Western Mining Technology Co.,Ltd.,Xining 810006,China;3.Qinghai Province Key Laboratory of Plateau Mineral Processing Engineering and Comprehensive Utilization,Xining 810006,China;4.Research Center of Nonferrous Mineral Resources of Engineering and Technology in Qinghai Province,Xining 810006,China;5.Sichuan Huidong Lead-Zinc Mine,Huidong 615205,China;
Abstract:A high-dirt lead-zinc ore in Huidong County,Sichuan Province contain main useful elements including 1. 01%Pb,6. 30% Zn,and 34. 89 g/t Ag with lead existing in galena and zinc in sphalerite respectively. The original process has not a good effect of zinc suppression when lead floats. Even the flotation technology is complicated,the indexes of lead concentrate and zinc concentrate are still worse. XKY-02,a new type of efficient inhibitor,was introduced,mixed with zinc sulfate to inhib-it zinc and float lead. Then,it was used to activate zinc concentration. With the grinding fineness of 80% passing 200 mesh, and by the process of one-roughing, two-cleaning and one-scavenging, and middling back to the flow-sheet, lead concentrate with lead grading 55. 77% Ag grade of 571. 72 g/t,6. 70% Zn and Pb recovery of 71. 05% and Ag recovery of 21. 17%,and zinc concentrate with zinc grade of 56. 06%,Ag grade of 244. 87 g/t,Pb 1. 04%,Zn recovery of 92. 59% and Ag recovery of 72. 99% were obtained respectively. Compared with the on-site process,the flow-sheet number is obviously less,but the index of the concentrates are greatly improved.
Keywords:Lead-zinc ore  Flotation  Inhibitor XKY-02