南水北调中线挖方渠段渗控措施优化研究
引用本文:崔皓东,张伟,张家发,吴德绪. 南水北调中线挖方渠段渗控措施优化研究[J]. 长江科学院院报, 2017, 34(12): 68-72. DOI: 10.11988/ckyyb.20161358
作者姓名:崔皓东  张伟  张家发  吴德绪
作者单位:1.长江科学院 水利部岩土力学与工程重点实验室,武汉 430010; 2. 国家大坝安全工程技术研究中心,武汉 430010; 3.长江勘测规划设计研究院,武汉 4300102
基金项目:国家重点研发计划项目,国家自然科学基金项目,水利部公益性行业专项,中央级公益性科研院所基本科研业务费项目
摘    要:南水北调中线工程中渗流调控是保障渠坡及衬砌板稳定的关键。为全面分析高地下水地区挖方渠段渗流调控措施合理性及优化的效果,针对典型渠段建立渗流模型,通过三维有限元数值模拟,研究渠道渗流场分布规律,比较不同措施的调控效果。结果表明:排水垫层结合逆止阀、排水板结合逆止阀、排水板结合衬砌板透水缝等3种排水措施都能有效降低渠底衬砌板下扬压力。最后比较了上述3种措施的差别,讨论了应用条件,提出了相应的建议,对类似工程有借鉴意义。

关 键 词:南水北调中线工程  挖方渠段  排水垫层  压力水头  渗控优化  数值模拟  
收稿时间:2016-12-28

Optimizing the Drainage System of Excavation Canal of the Middle Route Project of South-to-North Water Transfer in Expansive Soil Area
CUI Hao-dong,ZHANG Wei,ZHANG Jia-fa,WU De-xu. Optimizing the Drainage System of Excavation Canal of the Middle Route Project of South-to-North Water Transfer in Expansive Soil Area[J]. Journal of Yangtze River Scientific Research Institute, 2017, 34(12): 68-72. DOI: 10.11988/ckyyb.20161358
Authors:CUI Hao-dong  ZHANG Wei  ZHANG Jia-fa  WU De-xu
Affiliation:1.Key Laboratory of Geotechnical Mechanics and Engineering of Ministry of Water Resources, Yangtze River Scientific Research Institute, Wuhan 430010, China; 2.National Research Center on Engineering Technology of Dam Safety,Wuhan 430010, China; 3.Changjiang Institute of Survey Planning, Design and Research, Wuhan 430010, China
Abstract:Seepage field regulation is crucial for the stability of canal slope and liner plate along the middle route of the South-to-North Water Transfer Project,especially for stretches excavated in expensive soil area with high groundwater level.In this article,the seepage field of a typical section was simulated with 3-D finite element technology to investigate into the rationality and effectiveness of seepage regulation measures comprehensively.The distribution of seepage field was analyzed and the seepage control measures were compared.Results show that the uplift pressure on canal pavement would be reduced significantly by drainage cushion with drainage holes opening only when groundwater level is higher than the canal water level,by drainage cushion replaced by drainage board,and by drainage holes replaced with permeable joints of liner plate in addition.The differences in the three measures were compared,and their application conditions were discussed and corresponding suggestions were given.
Keywords:middle route project of South-to-North Water Transfer  excavation canals  drainage cushion  water pressure head  seepage field regulations  numerical simulation