摘    要:在第四纪弱胶结地层中建造较大断面的无压隧洞,国内的工程实践经验并不多.建造在第四纪西域砾岩(Q1)地层中的新疆玛纳斯河一级水电站引水隧洞,在勘测、设计、施工等方面的经验,可供类似工程参考.

关 键 词:第四纪地层  隧洞  玛纳斯一级水电站

Design and Construction of the Diversion Tunnel for Manas River I Hydropower Station
Zhou Jijun.Design and Construction of the Diversion Tunnel for Manas River I Hydropower Station[J].Water Power,2011,37(2).
Authors:Zhou Jijun
Affiliation:Zhou Jijun(Planning,Design and Research Institute of Xinjiang Production and Construction Corps,Shihezi 832000,Xinjiang,China)
Abstract:Constructing non-pressure tunnel with larger cross section in Quaternary weakly-cemented stratum is rare in China.The diversion tunnel of Manas River I Hydropower Station is constructed in the Quaternary conglomerate(Q1)in Xinjiang.The investigation,design and construction of the tunnel are introduced herein and the experiences can be as references to similar projects.
Keywords:Quaternary stratum  tunnel  Manas River I Hydropower Station  