白鹤滩水电站料场补充开采规划优选设计
引用本文:丁晓唐,覃牧,崔恩豪.白鹤滩水电站料场补充开采规划优选设计[J].水利水电科技进展,2018,38(5):43-47.
作者姓名:丁晓唐  覃牧  崔恩豪
作者单位:河海大学土木与交通学院;中国电建集团华东勘测设计研究院有限公司
摘    要:为解决白鹤滩水电站料场有用料储量不足的问题,依据储量复核结果,重点考虑现场地质条件、开挖面貌、扩挖时机、施工条件、经济性等因素,对补充开采规划方案进行了优选设计,并提出了3个补充开采规划方案。依据有用料储量、扩挖时机、施工条件、经济性4项评价指标,运用线性加权和法对3个方案进行了对比分析。结果表明,方案3为最优的规划方案,其扩挖后能增加有用料380万m3,可确保大坝混凝土工程骨料的供应,保障白鹤滩水电站的顺利建设。

关 键 词:白鹤滩水电站  料场  有用料  开采规划  线性加权和法
收稿时间:2018/4/25 0:00:00

Design and optimization of supplementary mining plans for aggregate storage in Baihetan Hydropower Station
DING Xiaotang,QIN Mu and CUI Enhao.Design and optimization of supplementary mining plans for aggregate storage in Baihetan Hydropower Station[J].Advances in Science and Technology of Water Resources,2018,38(5):43-47.
Authors:DING Xiaotang  QIN Mu and CUI Enhao
Affiliation:College of Civil and Transportation Engineering, Hohai University, Nanjing 210098, China,College of Civil and Transportation Engineering, Hohai University, Nanjing 210098, China and Power China Huadong Engineering Co., Ltd., Hangzhou 311122, China
Abstract:To solve the shortage of useful materials in Baihetan Hydropower Station aggregate storage, taking the site geological conditions, excavation features and time, construction conditions, and economy into consideration, three supplementary mining scheduling programs are designed and optimized based on the re-examined results of the storage. With the help of linear weighted sum(LWS)method, the proposed three mining plans are analyzed for comparison based on four evaluation indexes, including the reserved useful materials, excavation time, construction conditions, and economy. The result shows that the third exploitation plan is the best that can increase 3. 8 million cubic meters of useful materials after excavating. It ensures the supply of aggregate content for the dam concrete program and guarantees the construction of Baihetan Hydropower Station.
Keywords:Baihetan Hydropower Station  aggregate storage  useful materials  exploitation plan  linear weighted sum(LWS)method