首页 | 本学科首页   官方微博 | 高级检索  
     

陕西省引红济石调水工程1#支洞塌方原因分析及对策
引用本文:赵波.陕西省引红济石调水工程1#支洞塌方原因分析及对策[J].水资源与水工程学报,2006,17(5):58-60.
作者姓名:赵波
作者单位:陕西省石头河水库灌溉管理局,陕西,杨凌,712100
摘    要:塌方是隧洞施工过程中经常遇到的难题,本文针对引红济石工程1#支洞在施工过程中出现的两次塌方原因进行分析,总结出隧洞施工过程中避免塌方的主要方法和策略,具有普遍的借鉴意义。

关 键 词:水工隧洞  塌方分析  塌方防止对策
文章编号:1672-643X(2006)05-0058-03
修稿时间:2006年6月25日

Landslip causes analysis and countermeasures for the No.1 tunnel of "water transfer from Hongyan River to Shitou River" project
ZHAO Bo.Landslip causes analysis and countermeasures for the No.1 tunnel of "water transfer from Hongyan River to Shitou River" project[J].Journal of water resources and water engineering,2006,17(5):58-60.
Authors:ZHAO Bo
Abstract:Landslip is the key problem encountered in the tunnel project.Based on causes analysis for two landslides happened in No.1 tunnel construction of "Water Transfer from Hongyan River to Shitou River" project,some countermeasures to prevent landslide in the project operation have been summarized with reference to general occasions.
Keywords:hydraulic tunnel  landslip analysis  landslip prevention countermeasures  
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号