首页 | 本学科首页   官方微博 | 高级检索  
     

高海拔高地应力区深斜井施工导井开挖单价
引用本文:周峰,白现军,陈功民,刘章,侍克斌.高海拔高地应力区深斜井施工导井开挖单价[J].南水北调与水利科技,2012,10(1):142-144,149.
作者姓名:周峰  白现军  陈功民  刘章  侍克斌
作者单位:1. 新疆农业大学水利与土木工程学院,乌鲁木齐,830052
2. 葛洲坝新疆工程局有限公司,乌鲁木齐,830000
基金项目:国家高等学校博士点专项科研基金资助课题(200807580007);新疆水利水电工程重点学科基金资助项目(xjzdxk-2010-10-06)
摘    要:布仑口-公格尔水电站地处高海拔、高地应力区,其引水斜井是目前国内已建和在建中倾角最大的深斜井之一,工程施工难度大,存在很多不安全因素。在导井开挖施工中,成功使用自下而上全断面钻孔爆破-自重溜渣的施工导井开挖方法,保证了导井施工安全、质量和进度,施工导井已顺利贯通。单价分析结果为科学准确地控制此类工程施工消耗提供了详实的数据,也进一步表明该施工方法具有施工成本低、设备和技术简单等优点,具有很好的经济性,有推广和应用的价值。

关 键 词:高海拔区  高地应力区  深斜井  施工导井开挖  单价分析

Unit Price Analysis of Excavation of Pilot Shaft for Deep Inclined Shaft in an Area with High Altitude and Field Stress
ZHOU Feng , BAI Xian-jun , CHEN Gong-min , LIU Zhang , SHI Ke-bin.Unit Price Analysis of Excavation of Pilot Shaft for Deep Inclined Shaft in an Area with High Altitude and Field Stress[J].South-to-North Water Transfers and Water Science & Technology,2012,10(1):142-144,149.
Authors:ZHOU Feng  BAI Xian-jun  CHEN Gong-min  LIU Zhang  SHI Ke-bin
Affiliation:1(1.College of Water Conservancy and Civil Engineering,Xinjiang Agricultural University,Urumqi 830052,China; 2.Gezhouba Xinjiang Engineering Co.,LTD,Urumqi 830000,China)
Abstract:The Bulunkou-Konggur hydropower station is located in an area with high altitude and terrestrial stress,and its inclined diversion shaft has one of the biggest inclination angles among all the shafts already constructed and under construction.Therefore,it has many unsafe factors during the construction period.In the construction of pilot shaft,the excavation method of full-section borehole blasting from bottom to top-bad rock displacement with gravity is used,which ensures the security,quality and progress of the construction.The unit price analysis can provide the detailed data to control the construction consumption for these types of projects scientifically and accurately.The results showed that this method has several advantages,such as low cost and simple equipments and technology,thus it has potential to be popularized.
Keywords:high altitude area  high field stress area  deep inclined shaft  excavation of pilot shaft  unit price analysis
本文献已被 CNKI 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏