班多水电站施工导流设计
引用本文:林万旭,郭红彦,王永强.班多水电站施工导流设计[J].西北水电,2011(2):41-44.
作者姓名:林万旭  郭红彦  王永强
作者单位:中国水电顾问集团西北勘测设计研究院,西安,710065
摘    要:班多水电站技施阶段施工导流采用枯水期明渠分期导流方案,可尽早实现主河床截流,使得首台机组发电工期提前6个月,二、三期导流充分利用泄洪闸过流,减小了导流工程规模及投资,取得了较好的经济效益。

关 键 词:导流方式  导流标准  导流程序  导流明渠  围堰  班多水电站

Construction diversin design for Banduo hydropower project
LIN Wan-xu,GUO Hong-yan,WANG Yong-qiang.Construction diversin design for Banduo hydropower project[J].Northwest Water Power,2011(2):41-44.
Authors:LIN Wan-xu  GUO Hong-yan  WANG Yong-qiang
Affiliation:(Hydrochina Xibei Engineering Corporation,CHECC,Xi'an 710065,China)
Abstract:At the detailed design phase for Banduo hydropower project,the alternative of staged diversion by open channel in dry period is adopted for construction diversion,which can realize closure of the main river as early as possible,so that the first unit will be commissioned 6 months in advance.At the second and third stage diversion,flow is discharged through the flood discharge gate as much as possible,which reduces the investment and scale of diversion works,and obtains good economic benefits.
Keywords:diversion type  diversion standard  diversion procedure  diversion channel  cofferdam  Banduo hydropower project