摘    要:水利工程施工围堰的修筑,关系到工程建设的可行性和安全,直接影响到主体工程的工期和工程造价,从而影响到工程的经济效益和社会效益。禹门口一级站改扩建工程围堰采用土石混合围堰施工,填筑15 m高的水中临时施工围堰,为水中填土修筑高围堰积累了经验。

关 键 词:一级站改扩建  施工导流方案  土石混合围堰

Construction Diversion Design of Expansion Program of First stage Pumping Station in Yumengkou
YAN Hai-lei. Construction Diversion Design of Expansion Program of First stage Pumping Station in Yumengkou[J]. Shanxi Hydrotechnics, 2011, 0(1): 36-37
Authors:YAN Hai-lei
Affiliation:YAN Hai-1ei
Abstract:Construction of cofferdam of hydraulic engineering has bearing on the feasibility and security of hydraulic engineering construction,has direct impact on the construction duration of main project and the engineering costs,and finally affects the social and economic benefits of the engineering.Earth-rock cofferdam construction is adopted during the expansion program of first stage pumping station in Yumengkou,and a 15m high temporary cofferdam is constructed in water.All of these mentioned above have accumul...
Keywords:first stage pumping station  construction diversion scheme  earth-rock cofferdam  