摘    要:岩石巷道综合机械化快速掘进有助于改善采掘接续紧张的局面,而岩石硬度是影响综掘设备快速掘进的关键因素之一。针对硬岩巷道围岩岩性特点,利用超深孔预裂爆破技术,对硬岩巷道岩体强度进行弱化,并通过工程实践检验预裂效果,结果表明:硬岩巷道超深孔预裂爆破后,钻孔周围形成压碎区、裂隙区,使岩体有效强度降低,有利于综掘截割机具经济破岩;理论及数值模拟分析得出钻孔爆破后形成半径为1.8 m左右的松动破坏区;通过对新庄孜矿-812 m水平B4胶带大巷硬岩进行超深孔预裂爆破,钻孔窥视及工程验证爆破松动半径能够达到1.5~2.5 m之间,取得了良好的岩体强度弱化效果,为硬岩巷道机械化快速施工技术研究提供指导。

关 键 词:硬岩巷道  深孔预裂  强度弱化  机械化开采

Theoretical Analysis and Engineering Verification of the Range of Hard Rock Strength Weakening
FU Bao-jie,TU Min.Theoretical Analysis and Engineering Verification of the Range of Hard Rock Strength Weakening[J].Journal of Huainan Institute of Technology(Natural Science),2014(1):15-18,23.
Authors:FU Bao-jie  TU Min
Affiliation:1. Shool of Energy and Safety, Anhui University of Science and Technology, Huainan Anhui 232001, China; 2. The Key Labora- tory of Coal Mine Safety and Efficient Mining of Ministry of Education, Anhui University of Science and Technology, Huainan Anhui 232001, China)
Abstract:Fully mechanized rapid excavation in rock roadways is helpful to improve the intensive situation of the mining and driving continuance .One of the key factors is the rock hardness , which affects rapid excavation of fully mechanized equipment .Surrounding rock characteristics of hard rock roadways were concerned , the tech-nology of the pre-splitting blasting in deep boreholes was used to weaken hard rocks in roadways , and the engi-neering practice was carried out to examine the effect of pre -splitting .The results showed that after pre -split-ting blasting in deep boreholes , crushed and fractured zones appear around the boreholes , the effective strength of rocks were reduced in the crushed and fractured zones , which ensures economic breaking rocks by fully mech-anized cutting machines .Theoretical analysis and numerical simulation results showed that fractured zone with radius of about 1.8 m appeares after blasting .The technology was used to weaken hard rocks in B 4 belt convayor roadway at -812 m level in Xinzhuangzi Coal Mine .The results by observation in borehols and engineering veri-fication showed that blasting loosen radius reaches 1.5 m to 2.5 m, good weakening results were achieved , which provides important guidance for the mechanized rapid excavation technology research in rock roadways .
Keywords:hard rock roadway  deep hole pre-splitting  strength weakening  mechanized mining