金陵电厂取水方案的探讨 |
| |
引用本文: | 赵桂芳,曹守信.金陵电厂取水方案的探讨[J].山东电力高等专科学校学报,2009,12(1). |
| |
作者姓名: | 赵桂芳 曹守信 |
| |
作者单位: | 1. 山东电力工程咨询院,济南,250013 2. 山东电力研究院,济南,250002 |
| |
摘 要: | 本文题报告通过对长江水直流循环取水可能的两个方案即盾构法取水、顶管+沉管+钢制取水头取水,进行了技术论证、经济比较,通过比较论证认为盾构法取水方案更优。
|
关 键 词: | 取水 盾构 顶管 沉管 优化 |
Research on Scheme of Water-drawing for the Jinling Thermal Power Plant |
| |
Abstract: | According to technical argumentation and economical comparison for the two water-drawing schemes of direct-flow water circulation of Changjiang River:shield method,and the method of pipe jacking,sinking pipe,associated with steel intake works,this paper can conclude that the shield method is the optimum. |
| |
Keywords: | water-drawing shield tunnel method pipe jacking sinking pile optimizing |