风电与常规电源联合外送的受端可信容量研究
引用本文:张宁,康重庆,周宇田,陈治坪,李丹,陈之栩,刘军.风电与常规电源联合外送的受端可信容量研究[J].中国电机工程学报,2012(10):11+72-79.
作者姓名:张宁  康重庆  周宇田  陈治坪  李丹  陈之栩  刘军
作者单位:1. 电力系统及发电设备控制和仿真国家重点实验室清华大学电机系,北京市 海淀区 100084
2. 华北电网有限公司,北京市 西城区 100053
基金项目:国家高技术研究发展计划(863计划)资助项目(2011AA05A101)~~
摘    要:可信容量作为衡量电源对电力系统贡献程度的重要标志在电力系统规划中受到广泛关注,目前研究中往往仅考虑发电机组可靠性而忽略输电线路可靠性。针对中国风电与常规能源联合外送的实际情况,在可信容量的基础上提出能源基地受端可信容量的概念及其计算方法。对输电线路进行序列化建模,并利用基本序列运算实现了考虑输电线路可靠性的2节点电力系统生产模拟过程,进而评估能源基地各类电源对于受端电网的可信容量。采用加入风电后的IEEERTS-79算例测试了算法的有效性,同时研究了风电与常规能源联合外送情况下受端可信容量的影响因素。

关 键 词:风电  能源基地  受端可信容量  电力系统生产模拟  序列运算理论

Evaluation of Receiving-end Credible Capacity for Joint Delivery of Wind Power and Conventional Electricity Generation
ZHANG Ning,KANG Chongqing,ZHOU Yutian,CHEN Zhiping,LI Dan,CHEN Zhixu,LIU Jun.Evaluation of Receiving-end Credible Capacity for Joint Delivery of Wind Power and Conventional Electricity Generation[J].Proceedings of the CSEE,2012(10):11+72-79.
Authors:ZHANG Ning  KANG Chongqing  ZHOU Yutian  CHEN Zhiping  LI Dan  CHEN Zhixu  LIU Jun
Affiliation:1.State Key Lab of Control and Simulation of Power Systems and Generation Equipments (Dept.of Electrical Engineering,Tsinghua University),Haidian District,Beijing 100084,China; 2.North China Grid Co.Ltd.,Xicheng District,Beijing 100053,China)
Abstract:As a tool of measuring how much electricity generation contributes to system adequacy,the concept of credible capacity has received great attention in power system planning,especially on wind power.However,current evaluation ignores the outages of transmission lines.In China,several electric generation bases containing intermittent energy are planned to be delivered to load center through long transmission lines.With such background,this paper proposed the concept of receiving-end credible capacity.By modeling transmission line outages using sequence operation theory,two-node power system production simulation procedure was proposed.The model can be calculated efficiently and thus facilitates the evaluation of receiving-end credible capacity.Modified IEEE RTS-79 system was used to verify the validity of the proposed model.Impact factors of receiving-end credible capacity under the circumstance of wind power and thermal generation bundling delivery were studied.
Keywords:wind power  electric generation base  receiving-end credible capacity  power system production simulation  sequence operation theory
本文献已被 CNKI 万方数据 等数据库收录!