220kV电缆接入110kVGIS的特殊处理
引用本文:吕桂强,张卫峰.220kV电缆接入110kVGIS的特殊处理[J].广东输电与变电技术,2009,11(5):58-60.
作者姓名:吕桂强  张卫峰
作者单位:珠海电力设计院有限公司
摘    要:根据系统需要将220kV交联电缆降压运行接入110kVGIS的要求,提出了两种不同的设计方案。对方案的技术可行性和经济作比较,提出将220kV电缆经特殊处理,安装在110kVGIS端头的实施方案。实践证明,该方案行之有效,可作类似工程的参考。

关 键 词:220kV电缆  降压运行  电缆敷设

A Special Measure for Installing 220kV Power Cable Onto 110kV GIS
Lu Ouiqiang,Zhang Weifeng.A Special Measure for Installing 220kV Power Cable Onto 110kV GIS[J].Guangdong Power Transmission Technology,2009,11(5):58-60.
Authors:Lu Ouiqiang  Zhang Weifeng
Affiliation:Zhuhai Electric Power Design Institute Co. Ltd. Lu Guiqiang Zhang Weifeng
Abstract:Based on necessity of power system,220kV cable needs to join onto 110kV GIS for down-grade operation. Two design schemes are worked out. Comparison in technical tenability and economy is made. The scheme of making special treatment onto the 220kV cable to install into the 110kV GIS terminals is selected. Practice verifies that this scheme is effective in running and worth to be reference to the similar engineering afterward.
Keywords:220kV power cable Down-grade operating Cable laying  