首页 | 本学科首页   官方微博 | 高级检索  
     

C-MMC型电力电子变压器直流故障分析与保护方法研究
引用本文:孙建锋,徐云飞,周哲,李卫国,徐永海.C-MMC型电力电子变压器直流故障分析与保护方法研究[J].电测与仪表,2020,57(17):123-128.
作者姓名:孙建锋  徐云飞  周哲  李卫国  徐永海
作者单位:国家电网有限公司,先进输电技术国家重点实验室全球能源互联网研究院有限公司,先进输电技术国家重点实验室全球能源互联网研究院有限公司,先进输电技术国家重点实验室全球能源互联网研究院有限公司,新能源电力系统国家重点实验室华北电力大学
摘    要:对模块化多电平换流器 (Modular Multilevel Converter,MMC)型电力电子变压器的拓扑结构及实现原理进行介绍。分析了在采用半桥子模块的MMC中发生中压直流母线双极短路故障后的电流流通路径,以及其不能实现直流故障闭锁的原因。为解决上述问题,选取箝位双子模块代替半桥模块,并分析了其故障电流流通路径和故障闭锁原理。但由于箝位双子模块在直流故障闭锁后可能出现子模块过电压问题,为此,提出了电力电子变压器隔离级延时闭锁的策略,并分析了MMC闭锁后在该策略下隔离级闭锁前的故障电流流通路径。最后,通过PSCAD仿真平台对箝位双子模块的闭锁功能和隔离级延时闭锁策略进行了仿真验证。

关 键 词:电力电子变压器  直流故障  过电压  延时闭锁
收稿时间:2019/3/14 0:00:00
修稿时间:2019/3/14 0:00:00

Study on DC fault analysis and protection method of C-MMC based power electronic transformer
Sun Jianfeng,Xu Yunfei,Zhou Zhe,Li Weiguo and Xu Yonghai.Study on DC fault analysis and protection method of C-MMC based power electronic transformer[J].Electrical Measurement & Instrumentation,2020,57(17):123-128.
Authors:Sun Jianfeng  Xu Yunfei  Zhou Zhe  Li Weiguo and Xu Yonghai
Affiliation:State Grid Co,LTD,State Key Laboratory of Advanced Power Technology Global Energy Interconnection Research Institute Co,LTD,State Key Laboratory of Advanced Power Technology Global Energy Interconnection Research Institute Co,LTD,State Key Laboratory of Advanced Power Technology Global Energy Interconnection Research Institute Co,LTD,State Key Laboratory of Alternate Electrical Power System with Renewable Energy Sources North China Electric Power University
Abstract:The topological structure and implementation principle of modular multilevel converter (MMC) based power electronic transformer were introduced. The current path of the MMC with half bridge sub module in the presence of medium voltage DC bus double pole short circuit fault, and the reason why it can not achieve DC fault blocking were analyzed. In order to solve the above problems, the clamp double sub-module was selected to replace the half bridge sub module, and the fault current path and the fault blocking principle were analyzed. However, after the DC fault blocked, the overvoltage of the clamp double sub-module may occur. For this reason, the delay isolation strategy of isolated stage for power electronic transformer was put forward, and the fault current path before isolation and after MMC blocked was analyzed. Finally, the blocking function of clamp double sub-module and isolation level delay blocking strategy were simulated and verified by PSCAD simulation platform.
Keywords:power  electronic transformer  DC  fault  overvoltage  delay  blocking
点击此处可从《电测与仪表》浏览原始摘要信息
点击此处可从《电测与仪表》下载全文