三峡输变电工程调试成果总结
引用本文:杨万开,印永华,曾南超,王明新,种芝义,马为民,康 健.三峡输变电工程调试成果总结[J].电网技术,2008,32(15):5-10.
作者姓名:杨万开  印永华  曾南超  王明新  种芝义  马为民  康 健
作者单位:中国电力科学研究院,国网直流建设有限公司,湖北电力试验研究院
摘    要:从三峡输变电工程调试组织和内容体系的建立与完善、调试队伍的建立以及技术体系的建立与完善3个方面总结和分析了三峡输变电工程调试的组织成果,并对包括直流设备调试、分系统调试、站系统调试和系统调试主要成果的工程调试技术成果进行了分析。上述调试成果已在三峡输变电工程运行中得到了应用,并为以后输变电工程和特高压工程调试积累了技术资料。

关 键 词:三峡输变电工程  高压直流工程  调试
收稿时间:2008-01-16

Achievements Summary of Transmission and Transformation Project Commissioning Test for Three Gorges Power Station
YANG Wan-kai,YIN Yong-hua,ZENG Nan-chao,WANG Ming-xin,CHONG Zhi-yi,MA Wei-min,KANG Jian.Achievements Summary of Transmission and Transformation Project Commissioning Test for Three Gorges Power Station[J].Power System Technology,2008,32(15):5-10.
Authors:YANG Wan-kai  YIN Yong-hua  ZENG Nan-chao  WANG Ming-xin  CHONG Zhi-yi  MA Wei-min  KANG Jian
Affiliation:1.China Electric Power Research Institute,Haidian District,Beijing 100192,China; 2.State Grid Direct Current Project Construction Company Limited,Dongcheng District,Beijing 100005,China;
3.Hubei Electric Power Test Research Institute,Wuhan 430077,Hubei Province,China
Abstract:The organizational achievements obtained from the commissioning of power transmission and transformation project for the Three Gorges Hydropower Station are summarized in three aspects, i.e., the establishment and perfection of commissioning organization and its content system, the establishment of commissioning contingent and technical system, as well as the establishment and perfection of technical system. The technological achievements from engineering commissioning, including principal results in DC equipment or device debugging test, subsystem commissioning test, substation or converter system station commissioning test and system commissioning test, are analyzed. Above- mentioned commissioning test results have been applied in the operation of Three Gorges Power Transmission and Transformation Project, and technical data accumulated in this commissioning test is valuable for future commissioning test of power transmission and transformation project as well as that of UHV projects.
Keywords:Three Gorges power transmission and transformation project  HVDC power transmission project  commission
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《电网技术》浏览原始摘要信息