多时间尺度协调的区域控制偏差超前控制方法
引用本文:李予州,吴文传,张伯明,江木,肖岚,路轶.多时间尺度协调的区域控制偏差超前控制方法[J].电网技术,2009,33(3):15-19.
作者姓名:李予州  吴文传  张伯明  江木  肖岚  路轶
作者单位:李予州,吴文传,张伯明,江木,LI Yu-zhou,WU Wen-chuan,ZHANG Bo-ming,JIANG Mu(电力系统及发电设备控制和仿真国家重点实验室(清华大学电机系),北京市,海淀区,100084);肖岚,路轶,XIAO Lan,LU Yi(四川电力调度通信中心,四川省,成都市,610041)  
摘    要:根据机组响应控制指令时间长短不同,提出一种多时间尺度协调的区域控制偏差(area control error,ACE)超前控制方法。首先分析了现有ACE超前控制方法的不足,给出目标时刻控制区理想总发电的预测模型;然后分析了计划机组计划与执行的关系,提出计划机组出力偏差的预估方法;进而综合考虑总发电、计划机组发电和自动发电控制(auto generation control,AGC)机组的希望运行点,计算出目标时刻协调AGC机组的希望总出力;最后,通过一个优化模型把协调AGC机组的希望总出力分配到各协调AGC机组上。文章所提方法已在四川电网投入现场试运行,结果证明了该方法的可行性。

关 键 词:自动发电控制(AGC)  分解协调  控制性能标准  (CPS)  负荷预测  区域控制偏差(ACE)
收稿时间:2008-01-03

A Multi-Timescale Coordination Method for Area Control Error Advanced Control
LI Yu-zhou,WU Wen-chuan,ZHANG Bo-ming,JIANG Mu,XIAO Lan,LU Yi.A Multi-Timescale Coordination Method for Area Control Error Advanced Control[J].Power System Technology,2009,33(3):15-19.
Authors:LI Yu-zhou  WU Wen-chuan  ZHANG Bo-ming  JIANG Mu  XIAO Lan  LU Yi
Affiliation:1. State Key Lab of Control and Simulation of Power Systems and Generation Equipments (Dept. of Electrical Engineering,Tsinghua University),Haidian District,Beijing 100084,China;2. Sichuan Electric Power Dispatching Center,Chengdu 610041,Sichuan Province,China
Abstract:A multi-timescale coordination method for ACE-advanced control is proposed, which can consider the different response speed of various generators. Firstly, the deficiencies of the existing area control error (ACE)-advance control methods are analyzed and a novel model to forecast the ideal total power output within a control area is developed; secondly, the relation between the scheduling of scheduled generators and the executed results are analyzed, and an algorithm, which is used to predict the error between the scheduling and the actual output of the scheduled generators, is developed; and then, considering total output, the output of scheduled generators and the desired operation point of AGC generators, the desired total output of coordinated AGC generators at target time is calculated; finally, by means of an optimal model the desired total output of coordinated AGC generators is allocated to each coordinated AGC generator. The proposed method is put into on-site trail operation in Sichuan provincial power grid, and operation results prove that the proposed method is feasible.
Keywords:auto generation control (AGC)  decomposition and coordination  control performance standard (CPS)  load forecasting  area control error (ACE)