35 kV架空送电线路防雷用并联间隙研究
引用本文:陈维江,孙昭英,王献丽,李庆余,颜湘莲,王风雷,李红,王松虞,王增志,张文军.35 kV架空送电线路防雷用并联间隙研究[J].电网技术,2007,31(2):61-65.
作者姓名:陈维江  孙昭英  王献丽  李庆余  颜湘莲  王风雷  李红  王松虞  王增志  张文军
作者单位:1. 中国电力科学研究院,北京市,海淀区,100085
2. 北京电力公司,北京市,西城区,100023
摘    要:为解决35 kV架空送电线路的雷击问题,提出采用并联间隙防雷保护方案,分析了其保护原理,设计了35 kV线路防雷用并联间隙的结构尺寸;对并联间隙试品进行了大量的雷电冲击和工频电弧试验,结果表明并联间隙能有效保护绝缘子串和导线免于雷击引起的工频续流电弧的烧蚀;计算了带并联间隙线路的雷击跳闸率,建议将3片绝缘子增加为4片,加装并联间隙不会引起线路跳闸率增加。

关 键 词:35  kV架空送电线路  防雷保护  并联间隙  雷击跳闸率
文章编号:1000-3673(2007)02-0061-05
修稿时间:12 16 2006 12:00AM

Study on Shunt Gap Lightning Protection for 35 kV Overhead Transmission Lines
CHEN Wei-jiang,SUN Zhao-ying,WANG Xian-li,LI Qing-yu,YAN Xiang-lian,WANG Feng-lei,LI Hong,WANG Song-yu,WANG Zeng-zhi,ZHANG Wen-jun.Study on Shunt Gap Lightning Protection for 35 kV Overhead Transmission Lines[J].Power System Technology,2007,31(2):61-65.
Authors:CHEN Wei-jiang  SUN Zhao-ying  WANG Xian-li  LI Qing-yu  YAN Xiang-lian  WANG Feng-lei  LI Hong  WANG Song-yu  WANG Zeng-zhi  ZHANG Wen-jun
Affiliation:1. China Electric Power Research Institute, Haidian District, Bcijing 100085, China; 2. Bcijing Electric Power Corporation, Xichcng District, Bcijing 100023, China
Abstract:To solve the faults caused by lightning stroke in 35kV overhead transmission lines, it is proposed to use shunt gap as the lightning protection. The protective principle of shunt gap is analyzed and the structure and structural sizes of shunt gaps for 35kV overhead transmission lines are designed. A lot of lightning impulse and power frequency arcing tests are performed with shunt gap test specimen, and test results show that shunt gap can effectively make insulator strings and wires exclusive from ablation of power frequency arc incurred by lightning stroke. The lightning trip-out rate of 35 kV overhead lines with shunt gap is calculated, on this basis the authors recommend that when shunt gaps are equipped in 35 kV transmission lines, in order to restrict the increase of the lightning trip-out rate the number of insulator pieces in a single string should be changed from original three pieces into four pieces.
Keywords:35kV overhead transmission lines  lightning protection  shunt gap  lightning trip-out rate