Robust and stable flow shop scheduling with unexpected arrivals of new jobs and uncertain processing times
Authors:Donya Rahmani  Mahdi Heydari
Affiliation:Department of Industrial Engineering, Iran University of Science & Technology, P.C. 1684613114, Tehran, Iran
Abstract:In real scheduling problems, some disruptions and unexpected events may occur. These disruptions cause the initial schedule to quickly become infeasible and non-optimal. In this situation, an appropriate rescheduling method should be used. In this paper, a new approach has been proposed to achieve stable and robust schedule despite uncertain processing times and unexpected arrivals of new jobs. This approach is a proactive–reactive method which uses a two-step procedure. In the first step an initial robust solution is produced proactively against uncertain processing times using robust optimization approach. This initial robust solution is more insensitive against the fluctuations of processing times in future. In the next step, when an unexpected disruption occurs, an appropriate reactive method is adopted to deal with this unexpected event. In fact, in the second step, the reactive approach determines the best modified sequence after any unexpected disruption based on the classical objective and performance measures. The robustness measure is implemented in the reactive approach to increase the performance of the real schedule after disruption. Computational results indicate that this method produces better solutions in comparison with four classical heuristic approaches according to effectiveness and performance of solutions.
Keywords:Disruption  Uncertain processing time  Robustness  Stability  Flow shop  Proactive&ndash  reactive approach
本文献已被 ScienceDirect 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号