分期围堰导流的迭代法求解 |
| |
引用本文: | 吕兴祖,宗鸣.分期围堰导流的迭代法求解[J].电网与水力发电进展,1995(3). |
| |
作者姓名: | 吕兴祖 宗鸣 |
| |
作者单位: | 西安理工大学 |
| |
摘 要: | 分期围堰是常用的导流方式,导流初期河床被围堰束狭,造成上游水位的壅高。水流流态随纵向围堰长度与水头之比,可分为宽顶堰流与明渠流。考虑到电脑的广泛应用,本文推荐采用迭代法求解正常水深h0。临界水深hk及河糟缩窄后的水位壅高。
|
关 键 词: | 分期导流,水力计算,迭代法 |
Solution by Means of Iteration Method for Multi-phase Diversion |
| |
Authors: | Lu Xingzu Zong Ming |
| |
Affiliation: | Xian University of Technology |
| |
Abstract: | Cofferdam in stages is an ordinary diversion method during construction. At the earlystage of diversion, river channel is contracted by cofferdam and makes upstream water levelraised up higher.According to the ratio of the length of longitudinal cofferdam to the waterhead, broad weir flow and open channel flow are determined respectively. In the article, the iter-ation method is recommended for calculating normal water depth ho, critical water depth hk andraised upstream water level due to the contraction of river channel. |
| |
Keywords: | ulti-phase diversion Hydraulic computation Iteration method |