不良地质条件下长距离引水隧洞施工全过程进度仿真与实时控制研究
引用本文:胡连兴,钟登华,佟大威.不良地质条件下长距离引水隧洞施工全过程进度仿真与实时控制研究[J].岩土工程学报,2012,34(3):497-503.
作者姓名:胡连兴  钟登华  佟大威
作者单位:水利工程仿真与安全国家重点实验,天津 300072
基金项目:国家自然科学基金项目(90815019);国家自然科学基金创新研究群体科学基金项目(51021004);“十一五”国家科技支撑计划项目(2008BAB29B05)
摘    要:长距离引水隧洞常具有大埋深、长洞线、大洞径、高地应力水平、极其复杂的工程地质条件等特点 。大埋深和高地应力引起的岩爆及高涌水等地质问题对施工进度计划安排和控制影响非常大,尤其是对不良地质段的施工进度控制是整个工程能否按时完工的重中之重。结合循环网络的系统仿真与网络进度计划分析技术,提出了针对不良地质条件下长距离引水隧洞施工全过程进度仿真与实时控制方法。该方法可以对实时进度施工方案的变更和选择提供可行性研究和科学依据,为准确、迅速进行实时进度控制提供技术支持,增强实时施工进度的可控性。

关 键 词:长距离引水隧洞  不良地质  施工进度仿真  实时控制  
收稿时间:2011-07-29

Simulation and real-time control of whole construction progress of long-distance diversion tunnels under unfavorable geological conditions
HU Lian-xing,ZHONG Deng-hua,TONG Da-wei.Simulation and real-time control of whole construction progress of long-distance diversion tunnels under unfavorable geological conditions[J].Chinese Journal of Geotechnical Engineering,2012,34(3):497-503.
Authors:HU Lian-xing  ZHONG Deng-hua  TONG Da-wei
Affiliation:State Key Laboratory Hydraulic Engineering Simulation and Safety, Tianjin 300072, China
Abstract:The long-distance diversion tunnel is often characterized by great embedded depth,large hole diameter,long tunnel line,high ground stress and extremely complicated geologic conditions.Geologic issues like rock burst and high water gushing caused by big embedded depth and high ground stress have great influences on the construction schedule arrangement and control,especially the construction progress control for bad geological section,which is a key to the periodical completion of the whole project.Combined with the circular network system simulation and network project analysis technique,a simulation and real-time control method for the whole construction progress of long distance diversion tunnels under unfavorable geological conditions is presented.This method can provide feasible study and scientific basis for change and selection of real-time progress of construction scheme so as to realize accurate,fast real-time schedule control and to enhance the construction progress of real-time control.
Keywords:long-distance diversion tunnel  unfavorable geological condition  construction progress simulation  real-time control