华能玉环电厂1000 MW机组锅炉后炉膛安装方案
引用本文:相银涛. 华能玉环电厂1000 MW机组锅炉后炉膛安装方案[J]. 电力建设, 2008, 29(3): 76-78
作者姓名:相银涛
作者单位:天津电力建设公司,天津市,300012
摘    要:华能玉环电厂1 000MW机组锅炉后炉膛的安装, 重视各种设备的吊装顺序和预存方案。包墙入口集箱, 低过热器、再热器入口集箱以及省煤器中间集箱和入口集箱的预存, 降低了吊装难度, 减少了施工的危险性。采用地面组合的方式, 不仅减少了高空作业, 而且保证了组件整体安装质量。

关 键 词:1000MW机组  后炉膛  安装技术
文章编号:1000-7229(2008)03-0076-03
收稿时间:2010-01-25
修稿时间:2007-09-19

Boiler Rear Wall Installation Plans of Huaneng Yuhuan Power Plant 1000 MW Unit
XIANG Yin-tao. Boiler Rear Wall Installation Plans of Huaneng Yuhuan Power Plant 1000 MW Unit[J]. Electric Power Construction, 2008, 29(3): 76-78
Authors:XIANG Yin-tao
Abstract:During installation of Huaneng Yuhuan Power Plant 1 000 MW unit boiler rear furnace wall attentions were paid to the lifting sequences and pre-storage scheme for all various equipment,including inlet headers,LT superheater,reheater inlet headers and economizer intermediate headers and inlet headers.As a result,the difficulties of lifting operation and construction dangers were reduced.The ground assembling mode not only reduced the high air operation but also ensured whole installation quality.
Keywords:1 000 MW unit  boiler rear wall  installation technologys