平舒矿81112综采面采动影响下覆岩裂隙破坏规律研究
引用本文:姚晋宝1,' target='_blank'>2,杨昌永1,' target='_blank'>2,郝春生1,' target='_blank'>2,田庆玲1,' target='_blank'>2,邵显华1,' target='_blank'>2. 平舒矿81112综采面采动影响下覆岩裂隙破坏规律研究[J]. 中州煤炭, 2019, 0(5): 136-140. DOI: 10.19389/j.cnki.1003-0506.2019.05.030
作者姓名:姚晋宝1  ' target='_blank'>2  杨昌永1  ' target='_blank'>2  郝春生1  ' target='_blank'>2  田庆玲1  ' target='_blank'>2  邵显华1  ' target='_blank'>2
作者单位:(1.煤与煤层气共采国家重点实验室,山西 晋城 048012; 2.易安蓝焰煤与煤层气共采技术有限责任公司,山西 太原 030000)
摘    要:为达到高效抽采瓦斯,确保工作面安全生产的目的,同时充分合理利用瓦斯资源,针对平舒矿81112工作面,釆用理论分析、相似模拟、CDEM数值模拟,研究了采空区上覆岩层运动和裂隙分布规律,得到了工作面基本顶初次破断和周期破断距离,覆岩裂隙发育高度及演化形态,确定裂隙发育环三维位置和范围,确定高抽巷或高位钻孔及地面水平定向钻孔最佳的位置,达到高效抽采瓦斯的目的。

关 键 词:瓦斯抽采  覆岩运动  岩层裂隙  相似模拟  CDEM数值模拟

 Study on fracture failure law of overlying strata under mining on 81112 fully-mechanized working face of Pingshu Mine
Yao Jinbao1,' target='_blank'>2,Yang Changyong1,' target='_blank'>2,Hao Chunsheng1,' target='_blank'>2,Tian Qingling1,' target='_blank'>2,Shao Xianhua1,' target='_blank'>2.  Study on fracture failure law of overlying strata under mining on 81112 fully-mechanized working face of Pingshu Mine[J]. Zhongzhou Coal, 2019, 0(5): 136-140. DOI: 10.19389/j.cnki.1003-0506.2019.05.030
Authors:Yao Jinbao1  ' target='_blank'>2  Yang Changyong1  ' target='_blank'>2  Hao Chunsheng1  ' target='_blank'>2  Tian Qingling1  ' target='_blank'>2  Shao Xianhua1  ' target='_blank'>2
Affiliation:(1.State Key Laboratory of Coal and CBM Co-mining,Jincheng 048012,China;2.Yi′an Lanyan Coal and Coal-bed Methane Co-mining Technology Co.,Ltd.,Taiyuan 030000,China)
Abstract:In order to achieve the goal of high-efficiency gas extraction and ensure the safe production of working face,and make full and rational use of gas resources,aiming at 81112 working face of Pingshu Mine,using theoretical analysis,analogy simulation and CDEM numerical simulation,the movement of overburden strata and the distribution law of cracks in goaf are studied,the primary and periodic breakage distances of basic roof,the height and evolution form of overburden cracks are obtained,the three-dimensional position and scope of crack development ring are determined,and the high-level extraction roadway or high-level boreholes and horizontal orientation of surface are determined,the optimum location of boreholes can achieve the goal of high efficiency gas extraction.
Keywords:  gas drainage   overburden stratum movement   strata fracture   similar simulation   CDEM numerical simulation