Experience gained from the development and results from tests of the equipment of the Kalinin NPP Unit 4 regeneration and intermediate steam separation and reheating system
Authors:N. N. Trifonov  Yu. G. Sukhorukov  V. F. Ermolov  F. A. Svyatkin  E. K. Nikolaenkova  T. G. Sintsova  E. B. Grigor’eva  S. B. Esin  M. G. Ukhanova  E. A. Golubev  S. P. Bik  V. B. Tren’kin
Affiliation:1. Polzunov Central Boiler-Turbine Institute Research and Production Association, Atamanskaya ul. 3/6, St. Petersburg, 191167, Russia
2. Kalinin Nuclear Power Plant, a Branch of Rosenergoatom Concern, Udomlya, Tver oblast, 171841, Russia
3. ZiO-Podolsk, Zheleznodorozhnaya ul. 2, Podolsk, Moscow oblast, 142103, Russia
Abstract:The equipment of the Kalinin NPP Unit 4 regeneration, intermediate separation, and steam reheating (ISSR) systems is described and the results of their static and dynamic tests are presented. It was shown from an analysis of test results that the equipment of the regeneration and ISSR systems produce the design thermal and hydraulic characteristics in static and dynamic modes of its operation. Specialists of the Central boiler-Turbine Institute Research and Production Association have developed procedures and computer programs for calculating the system of direct-contact horizontal low-pressure heaters (connected according to the gravity circuit arrangement jointly with the second-stage electrically-driven condensate pumps) and the ISSR system, the results of which are in satisfactory agreement with experimental data. The drawbacks of the layout solutions due to which cavitation failure of the pumps may occur are considered. Technical solutions aimed at securing stable operation of the equipment of regeneration and ISSR systems are proposed. The process arrangement for heating the chamber-type high-pressure heaters adopted at the Kalinin NPP is analyzed. The version of this circuit developed at the Central Boiler-Turbine Institute Research and Production Association that allows the heating rate equal to 1°C/min to be obtained is proposed.
Keywords: