酸刺沟煤矿综放工作面矿压显现异常及控制技术
引用本文:许红杰,邢国富,徐天发.酸刺沟煤矿综放工作面矿压显现异常及控制技术[J].煤炭科学技术,2012(7):21-23,34.
作者姓名:许红杰  邢国富  徐天发
作者单位:天地科技股份有限公司开采设计事业部;内蒙古伊泰京粤酸刺沟矿业公司;内蒙古伊泰煤炭股份有限公司工程管理部
摘    要:针对酸刺沟煤矿6上煤层大采高综放工作面矿压显现强烈,对工作面矿压显现进行了实时在线监测与分析。结果表明:工作面周期来压步距为20.2 m,来压动载系数平均1.35,高压力区集中在20—130号支架,98%的支架日最大工作阻力达到或超过15 000 kN的额定工作阻力,工作面推采初期出现压架事故。采取了提高安全阀开启阀值、加快推进速度、来压期间减少放煤和在高压力区深空卸压爆破等措施控制顶板,减小压力显现强度,监测显示安全阀开启率降低至12.4%,支架工作阻力基本符合正态比例分布,提高了工作面安全生产水平。

关 键 词:大采高  综放工作面  矿压显现  压架事故  在线监测

Abnormal Mine Pressure Behavior and Control Technology of Fully Mechanized Top Coal Caving Mining Face in Suancigou Mine
XU Hong-jie,XING Guo-fu,XU Tian-fa.Abnormal Mine Pressure Behavior and Control Technology of Fully Mechanized Top Coal Caving Mining Face in Suancigou Mine[J].Coal Science and Technology,2012(7):21-23,34.
Authors:XU Hong-jie  XING Guo-fu  XU Tian-fa
Affiliation:1.Mining and Design Department,Tiandi Science and Technology Company Ltd.,Beijing 100013,China;2.Inner Mongolia Yitai Jingyue Suancigou Mining Company,Ordos 017000,China;3.Engineering Management Department,Inner Mongolia Yitai Coal Company Ltd.,Ordos 017000,China)
Abstract:According to the serious mine pressure behaviors in the high cutting fully mechanized top coal caving mining face in No.6 Up seam of Suancigou Mine,a real time online monitoring and measuring and analysis was conducted on the mine pressure behaviors of the coal mining face.The results showed that the periodical pressure step distance of the coal mining face was 20.2 m,the average pressure dynamic coefficient was 1.35 and high pressure zone was concentrated on No.20 to No.130 hydraulic powered supports.The daily max working resistance of the 98% powered supports would reach or be over the rated working resistance of 15 000 kN.There was a powered support jammed accident occurred at the initial mining period of the coal mining face.According to above problems,the measures of the safety valve open value increased,advancing speeded up,less top coal caving during the pressure period,deep pressure releasing blasting and others were applied to control the roof pressure behavior strength.The monitoring and measuring showed that open and start rate of the safety valve was reduced to 12.4%.The working resistance of the powered supports basically could meet the normal percentage distribution and could improve the safety production level of the coal mining face.
Keywords:high cutting height  fully mechanized top coal caving mining face  mine pressure behavior  hydraulic powered support jammed accident  on-line monitoring and measuring