EPC项目进度计划的编制与进度控制
引用本文:李玉国,段凤贤,康久常.EPC项目进度计划的编制与进度控制[J].当代化工,2011(12):1261-1264.
作者姓名:李玉国  段凤贤  康久常
作者单位:中国寰球工程公司辽宁分公司
摘    要:叙述的是项目一、二、三、四级进度计划的编制时机及主要内容,编制各级计划时应注意的问题.订货资料的返回时间的确定,重点是设计周期与采购周期的确定.设计、采购、施工等过程控制的重点及注意事项.

关 键 词:进度计划  进度控制  MR文件  设计周期  采购周期  费用控制

Compilation of EPC Project Schedule Plan and Schedule Control
LI Yu-guo,DUAN Feng-xian,KANG Jiu-chang.Compilation of EPC Project Schedule Plan and Schedule Control[J].Contemporary Chemical Industry,2011(12):1261-1264.
Authors:LI Yu-guo  DUAN Feng-xian  KANG Jiu-chang
Affiliation:(China Huanqiu Contracting & Engineering Corporation Liaoning Company,Liaoning Fushun 113006,China)
Abstract:Compilation and main contents of No. 1, No.2, No.3, No.4 step project schedule plan were introduced, and some problems during the compilation were discussed, such as determining the time when ordering data were returned, determining the design cycle and procurement cycle, other emphases during design, procurement and construction.
Keywords:Schedule plan  Schedule control  MR document  Design cycle  Procurement cycIe  Cost control