RH精炼过程Al2O3夹杂物运动和去除的数值模拟
引用本文:艾新港,王春松,孟凡童,李胜利,刘海啸,甘雨. RH精炼过程Al2O3夹杂物运动和去除的数值模拟[J]. 钢铁研究学报, 2016, 28(1): 20-24. DOI: 10.13228/j.boyuan.issn1001-0963.20140417
作者姓名:艾新港  王春松  孟凡童  李胜利  刘海啸  甘雨
作者单位:1. 辽宁科技大学材料与冶金学院,辽宁鞍山,114083;2. 辽宁科技大学化学冶金辽宁省重点实验室,辽宁鞍山,114083;3. 辽宁科技大学冶金工程辽宁省重点实验室,辽宁鞍山,114083
基金项目:国家自然科学基金资助项目(51374125),辽宁省教育厅资助项目(L2015251),辽宁省大学生创业训练计划资助项目(201510146007)
摘    要:在流场模拟计算的基础上,建立了RH真空精炼过程Al2O3夹杂物运动及去除模型.通过数学模拟计算,分析了RH精炼过程夹杂物运动规律,讨论了夹杂物尺寸、RH吹气量等对夹杂物去除的影响.研究结果表明:同一管径条件下,吹气量为1 400 L/min时,夹杂物的总去除率最高为66.1%且最快去除时间为202 s,是去除夹杂物的最优吹气量;同一吹气量条件下,下降管内径为700 mm时,夹杂物的去除率最高,可达71.31%,夹杂物去除时间最短,为217s.

关 键 词:RH  Al2O3夹杂物  去除率  粒径

Numerical simulation of Al2O3 inclusion movement and removal in RH refining process
AI Xin- gang,WANG Chun- song,MENG Fan- tong,LI Sheng- li,LIU Hai- xiao,GAN Yu. Numerical simulation of Al2O3 inclusion movement and removal in RH refining process[J]. Journal of Iron and Steel Research, 2016, 28(1): 20-24. DOI: 10.13228/j.boyuan.issn1001-0963.20140417
Authors:AI Xin- gang  WANG Chun- song  MENG Fan- tong  LI Sheng- li  LIU Hai- xiao  GAN Yu
Affiliation:1. School of Materials and Metallurgy, University of Science and Technology Liaoning, Anshan 114083, Liaoning,China ;2. Key Laboratory of Chemical Metallurgy Engineering, University of Science and Technology Liaoning, Anshan 114083, Liaoning, China ;3. Key Laboratory of Metallurgy Engineering, University of Science and Technology Liaoning, Anshan 114083, Liaoning, China
Abstract:Based on the flow field simulation,a model for simulating the Al2 O3 inclusion movement and removal in RH refining process was established.Through the mathematical simulation calculation,the movement law of inclusion in RH was analyzed.Moreover,the effects of inclusion size and air-blowing rate on the inclusion removal were discussed.The results show that under the conditions of the same pipe diameter,the highest removal rate and shortest removal time is 66.1 % and 202 s respectively with the gas blowing rate 1400 L/min,which is also the optimal gas blowing rate.While under the conditions of the same air-blowing rate,the removal rate of inclusion in downcomer with 700 mm in diameter is the highest as 71.31% and the shortest inclusion removal time is 217 s.
Keywords:RH  Al2O3 inclusion  removal rate  particle size