Removal of Redundant Relationships in an AON Project Network for Evaluating Schedule Complexity
Authors:H. A. Bashir
Affiliation:Dept. of Mechanical and Industrial Engineering, Sultan Qaboos Univ., P.O. Box 33, Al-Khod, 123 Muscat, Oman. E-mail: hamdi.bashir@mail.mcgill.ca
Abstract:Since redundant relationships in an activity-on-node (AON) project network indicate that the schedule is more complex than it actually is, they should not be considered when evaluating the schedule complexity. However, identifying the relationships that can be removed while maintaining the project logic is not an easy task. For this purpose, this paper proposes a methodology, adapted from interpretive structural modeling, that basically transforms an AON project network into a network called minimum-edge diagraph which contains no redundant relationships. The methodology steps are explained through a demonstrative example of a simple hypothetical project. The application of the methodology to the AON network of a real construction project shows that it is easy to use yet effective in removing redundant relationships.
Keywords:Project management  Scheduling  Construction management  
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号